Project environments are dynamic, and changes are constant in areas like process, planning, or scope. You can group these changes into two categories:
- Change Management
- Configuration Management
“Change Management” is the first category. Here you manage changes related to project management plans, processes, and baselines.
In the second category, you manage changes related toproduct scope, known as configuration management.
Change requests are required when baselines are established, and you have to make changes to them. If the baselines are not set, no formal change request is required. Change requests and configuration requests are part of the integration management system.
Change management is a well-known term in project management, but configuration management is not. In the IT field, the term ‘configuration management’ is used frequently, so if you are not in this industry, you may face issues with understanding the concept.
As a non-IT professional, I had this struggle. However, now that I have passed the PMP and PMI-RMP exams, I can help you understand the concepts in this blog post.
Please note that change management and configuration management are the most important concepts for thePMP exam,您将在上面看到许多问题。
变更管理系统
根据PMBOK指南第六版,“变更控bob手机客户端制侧重于识别,记录和控制更改the projectand the project baselines.”
在变更管理系统中,您可以管理与项目范围,计划和基准相关的更改。
例如,您用光了资金,需要额外的资金来完成该项目,因此,您将提出更改请求,以供额外资金。或者,您可能无法在指定的时间内完成项目,并且需要时间延长。
In the change management system, the change request is analyzed for any possible impact on any other project objectives. Afterward, the request is either approved or rejected.
To minimize disruption, a change management system must ensure that all parameters are identified and analyzed for any possible impact.
If the change request is approved, you will update the concerned baseline, update the project documents, and inform the concerned stakeholders.
Change Management Activities
You do the following during change management:
- Identify the changes.
- Prepare proper documentation for the changes.
- Review, analyze, and make a decision for the change request.
- Make sure that the request is implemented, registered, and communicated.
Configuration Management System
根据PMBOK指南第6版,“配置控bob手机客户端件侧重于可交付成果和流程的规格。”
In the configuration management system, you manage the changes related to the product specification and the process.
For example, suppose you are developing a product and the client requests the addition of some extra features.
Since this change is related to the configuration of the product, you will deal with this change using the configuration management system.
Configuration management documents how you will monitor and control changes. It is a process of defining configurable items (product, service, result, and component) and controlling changes to such items.
The configuration management plan keeps version control of the product. Here you can keep a log of all the changes made to any version of the product for review.
Configuration Management Activities
You do the following during configuration management:
- Identify the configurable items.
- 记录并准备所有可配置项目的报告。
- Verify and conduct an audit of all configurations are as per the requirements.
A Real World Example of Change and Configuration Management
Suppose you are working on a project to construct a school building with ten classrooms.
Case: 1
During the middle of the project, your contractor for steelwork walks off the job and you have to find a replacement. You find an alternative, but the new contractor will not start working on your project for a week.
这个项目将推迟。Therefore, you will raise a change request for a one-week extension of the schedule through the change management system.
Once this request is approved, you will update your schedule baseline.
This is an example of the change management system.
Now let us look at an example of the configuration management system.
Case: 2
You are constructing a school building, and the client requests that you increase the number of rooms from ten to fifteen.
This is a request to change the product scope as the client has altered the product configuration.
You will handle this change under the configuration management system because here the specifications of your product have changed. Earlier, the school building had ten rooms, and now it will have fifteen rooms.
请注意,在第一种情况下,你提高了change request to increase the deadline of the project by one week. There was no change to the product, the change was only needed in the schedule baseline; the school building was the same, but you will hand over this building to the client one week later.
The Difference Between Change Management and Configuration Management Systems
The main difference between the change management and configuration management systems is that change management deals with processes, plans, and baselines, while configuration management deals with product specifications.
An example of a change management system can be additional funding requirements or a schedule extension, while an example of configuration management can be an extra feature added to the product.
Conditions for Change Management
The following are a few conditions for change management:
- Delay in schedule: You will have to develop a new schedule reflecting the current situation.
- 成本超支:您需要重新估计您的成本才能完成该项目。
Conditions for Configuration Management
The following are a few conditions for configuration management:
- Market competition forces new features on the product.
- The project took so long that the product is obsolete, so an update is required.
- The client requested you add some extra functions.
- Due to cost overrun, some features are removed from the product.
- To complete the project early, some features are removed.
Change Management Vs Configuration Management
Change management and configuration management do not compete for the same space. They are used for different purposes.
According to the PMBOK Guide 6th edition, “Configuration control is focused on the specification of both the deliverables and the processes, while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.”
Any change in product configuration will also affect the project scope, and you will update your project plans, cost, and schedule baselines.
Configuration management has a larger scope than change management.
谁可以提出更改和配置请求,谁可以授权?
Anyone can raise a change request but it must be approved by the project manager or a higher authority, as mentioned in the configuration or change management plan. If the client is not involved in the process, their consent is required to implement the change request.
A higher authority can be a Change Control Board (CCB), Project Management Office (PMO), or any other stakeholder as mentioned in the project management plan.
Regarding a configuration request, usually, it comes from the client as it involves a change in the product.
This request is reviewed by the project manager and then forwarded to the concerned higher authority for their review and approval. An agreement from the client may be required because they have to pay for any additional features.
Summary
Change management and configuration management are part of integration management and both deal with all the changes that can happen within the project or the product. Change management relates to changes related to the plan, process, and baselines, while configuration management deals with changes related to the product scope. The job of the project manager is to raise these requests and ensure that they are properly reviewed. Once the decision is made, it should be implemented immediately.
Now I hope you will not have any problem in solving questions on the PMP exam regarding change management and configuration management systems.
How do you manage changes in your project? Please share your experiences through the comments section.
Hello Fahad,
谢谢for your well thought out article.
I like your definitions, and seems correct; and certainly one way to interpret the PMBOK. But, part of the problem (and why you have written this article and folks like me and rest of your readers look for clarification), is that the PMBOK very much makes it all a fuzzy deal. Your definition is good and makes perfect sense—it’s what I’d also espoused to: Configuration has to do with Product; Change has to do with Project docs, baselines, processes, etc. But there are contradictions.
And, as I’ve tried to make sense of it in my own head in studying PMBOK (as you know PMI has “THEIR definition” of things, not always the same as “Organization/Company lambda’s”), there are some contradictions in PMBOK, and thus in your own definitions above—which are indeed direct out of PMBOK. You say that “Change Control” is about “Project stuff” — Project Documents, Baselines and Processes ; and “Configuration Control” as Product/Scope related (“Product Stuff”). Yet, you then correctly quote PMBOK that ““Configuration Control focuses on the specifications of both the deliverables and the processes” (i.e., note PROCESSES).
Further on, you point again to the contradiction when you quote PMBOK: “Configuration control is focused on the specification of both the deliverables and the processes (i.e., note PROCESS!), while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines” (note DELIVERABLES!). Thus not in line with your stated interpretation / defintition.
Another interpretation (that I’ve enountered) is that Change Control is the process of changing Project “Artifacts” (Project document, plans, process, deliverables, baselines – in short, everything that is under control): the written change requests, the Change Control Board, voting, approval / rejections, etc. And that Configuration control is the versioning, identification of “current version”, archiving of old versions, etc. of all “Project Artifacts” (Artifacts covering both “Project Stuff” like docs & processes and “Product Stuff”, like deliverables). This is the one espoused by Rita Mulcahey (her PM book). This interpretation also has problems and contradictions with some of the same definitions (and others) of Change Control (and Change Mgmt) and Configuration Control (and Config Mgmt) that is found in PMBOK.
All this to say: PMBOK was written by a lot of folks and then “Controlled” over its various authors and chapters to ensure overall integrity. But there remain unclarities and contradictions – and I believe this is one. They seem to clear these up with new versions of PMBOK, but others appear. All this said, your definition is a good one – and one that I have always thought was true. Now I am beginning to wonder. Having read around and now studying for PMBOK — and thus trying to understand “How does PMBOK define this” – because as stated earlier PMBOK definition is not always same one’s “real world” definition. That’s okay, it’s just not okay with they are not clear and there are contradictions in their method. Thanks. Great article. If you can or in position to dialogue with them– tell PMI to clarify their defintiions! Look forward to your feedback.
变更管理”是第一类。在这里,您可以管理与项目管理计划,{Processes}和基线有关的更改。
According to the PMBOK Guide 6th edition, “Configuration Control focuses on the specifications of both the deliverables and the {processes}.”
I don’t understand how the 2 terms dealing with{ process }
kindly clarify it.
Hello Anas,
Change management is a subset of configuration management.
Hi Mr. Fahad,
Now, if the client request change in my scope,
我需要并行进行变更管理和配置管理
Hello Anas,
我相信他要求更改产品范围。在这种情况下,您将进行配置管理。
Hi Fahad,
Changing the product scope, won’t it be required then to change the schedule and cost baseline? As product scope increases, cost and time increases right. Then, we have to work on both Configuration management followed by Change Management, isn’t?
Change management is a part of configuration management.
Does the Configuration Management, lead to raise a Change request in Project Management ?
Below are same 2 examples used in here, to help you understand, what I am trying to convey.
Example 1
在项目中间,我的钢铁工作承包商脱离了工作,我必须找到一个替代品。我找到了另一种选择,但是新承包商将在一个星期内开始从事该项目。
这个项目将推迟。因此,我将意大利广播电视公司se a change request for a one-week extension of the schedule through the change management system.
Example 2
Now, I am constructing a school building and the client requests that I have to increase the number of rooms from ten to fifteen.
This is a request to change the product scope as the client has altered the product configuration.
I will handle this change under the configuration management system because here the specifications of the product have changed. Earlier the school building had ten rooms, and now it will have fifteen rooms.
However, building additional 5 rooms will take more time than building 10 rooms, planned earlier. Hence, my schedule will also change as a result effecting my baseline, and so I have to raise a change request.
Please let me know if my understanding is correct !
In both cases, you will raise a change request.
Very well explained. Thank you
You are welcome Harshala.
That’s a great one brother. Many thanks for making me understand these concept better in this context.
You are welcome Muhammed.
Partly wrong explanation…
Hello Tunc, what part is wrong?
Fantastic !
谢谢Babak.
很棒的解释,您清楚地指出了我在这部分的混乱。太感谢了。
You are welcome Kenny.
very useful
谢谢Shriram for your comment.
Thanks.
Change management deals with project scope while Configuration management deals with product scope.
Correct.
400 questions are in simulation?
Hello Mahfuz,
In the PMP Question Bank you will find 400 Questions. The PMP Mock Test has 200 questions.
ASC Fahad, thanks in million Brother for your great and Briliant mind for providing us this wealthy knowledge,
Wasalaam Ishmael,
Thanks for your comment.
Great writeup. The configuration management is new to me and your post was useful. Thanks.
Anwar
Janbi.me
You are welcome Anwar.
This article is very good. It helps me to get clear about Configuration management and Change Request.
So, I would like to confirm about our project.
My project is to build the Window with blue color. But in executing, The window was painted with blue color. After that the stakeholder changed the color to yellow.
So, this should be managed by Change management or Configuration Management.
因为它会影响时间表,成本和产品规范。
Please explain.
Thank You so much.
This is the change in the specification, so configuration management.
Hello Fahad,
Please Read this sections from the PMBOK® Guide Sixth Edition, and then correct your answer and please also try to understand it well. What you are saying about configuration management and change management isn’t True at all.
“Configuration management plan:
Describes how the information about the items of the project (and which items) will be recorded and updated so that the product, service, or result of the project remains consistent and/or operative.
“变更控制should be applied once the first version of a deliverable has been completed. The control of the multiple versions or editions of a deliverable (e.g., documents, software, and building blocks) is supported by configuration management tools and procedures.”
“在建立基准之前,不需要更改由性能集成更改控制过程正式控制。一旦项目底线,更改请求就会完成此过程。一般而言,每个项目的配置管理计划应定义需要将哪些项目工件放在配置控制下。配置元素中的任何更改均应正式控制,并需要更改请求。”
“Configuration management activities such as: how changes will be initiated; how impacts will be analyzed; how they will be traced, tracked, and reported; as well as the authorization levels required to approve these changes;”
谢谢.
Hello Shady, though more technical details can be added to this blog post, the points discussed here are valid.
Mean is 20.0
Apply rule of 7,the output data are out of control and need investigation.
Hi Fahad, i also have same question above that why change management is a subset of configuration management instead another way around. Is there any reasoning behind?
Also have another question which made me confuse,
Ques: project manager doing quality check for steel bolts of 20 cm. The acceptable control limits are 19.955 cm and 20.045 cm. The measurements made at the end of the process yielded the following results : 20.033 cm, 19.982 cm, 19,995 cm, 20.006 cm, 19.970 cm, 19.968 cm, 19.963 cm, 19.958 cm, 19.962 cm, 19.979 cm and 19.959 cm. What should be done?
I always think if control limits are good why we need to frther investigate the process? Is it not control limits are typically similar like tolerances (except prior is defined by PM and later by customer.)
Thanks
Sumit
Configuration management has larger scope as compared to change management.
控制限制是由项目管理器设置的,以控制该过程,如果有任何内容,他将检查尽管项目在可接受的范围内,但一切都正确。
In my view , change in the configuration may also impact cost,schedule baseline & or may invoke some risks . In such situation change management needs to be initiated based on the impacts. Hence, change management can be a subset of configuration.
Please share your thoughts about my views .
Change management is a subset of configuration management.
Can you explain why the change management system is a subset of the configuration management system?
While opposite can be true but how change management system falls under configuration management system.
This is as per the definition which was defined by the PMI.
Dear Fahad,
Can you please provide a reference to this from PMI..?
If you have access to the PMBOK Guide 5th edition, you can refer to page 532.
感谢Fahad的解释,但是根据您的解释,一个问题主要用于产品和更改主要集中在基线和项目计划上,因此我看到,在许多方面,它们都会聚在一起,例如对于您的情况2现在需要将教室数量从10个更改为20个,现在可以更改产品,但是要满足该产品,您也需要更改计划,因此,在这种情况下,我们将通过配置和更改,如果我错了
Thanks again
In short, change management is a subset of configuration management.
哇,这很有趣和声音
thank you.
You are welcome Lungile.
Any changes in the project management plans and all its subsidiary plans and baselines requires to be updated through change control process and have it approved. Then do all project documents would need to go through the change control process before updates can be made? e.g. stake holder register or risk register or requirement documents. Can these by updated without going through a formal change control process and approval? Can the PM make the changes without some else’s approval?
These are the project document and supposed to be updated all the time throughout the project lifecycle. They do not require to go through this process.
Then are all project documents treated the same way? There is a list of documents in the PMBOK guide page 78. Besides the obvious ones like performance data and issues/change log/forecast etc, all others can be updated without a formal change control approval?
As per my understanding – yes.
Thanks so much Fahad for this piece, it brings simplicity and gives clarity to differentiate between Configuration and Change Management System.
You are welcome Kemisola.
Dear
谢谢very murch for the nice explanition.
Really I like it specially that I am starting the course of PMP preparation for the PMP exam.
谢谢,富丽堂皇。
Abdulmohsen
Thanks Abdulmohsen for your visit and leaving comment.
thanks, very clear now
You are welcome Aleciri.
I don’t agree this clarification, PMBOK does not very clearly distinct the two, my impression is that configuration management is super set of change manamement, plus some document record repository functions.
Okay.
can we say that change in spécifications (configurations) can be similar to change to product quality attributes? what is the difference between both of them? please i need clarification
thanks in advance !
What do you mean by product quality attribute?
我认为配置管理基本上是如何will you manage the ‘integrity’ of your products/artifacts, how will all the stakeholders know what’s the latest blueprint to reference, what’s the latest architecture diagram, what’s the latest design document, what’s the latest source code to act one, etc.
The Change Management is just any changes, even the ones which doesn’t result in any change to Scope, Cost, Schedule.
Please read the blog post again.
Good explanation. Fahad, thank you and also others who have contributed.
You are welcome Jaleel.
Thanks a lot. and also to those who contribute in comments.
Your explanations clear my understandings.
谢谢all.
You are welcome Maythawda.
你好,
Change Management = Project Change.
Configuration Management = Product Change .
Ri8?
Right.
Configuration management system is the system defining what your final product look like in specific and technical details.
Change control system: the set of procedures and processes that you need to apply in order to make a change
great work Fahad. this was helpful to me
Thanks Joseph.
I find a similar article on linkedin, and it is matching word by word. You can have a look at it:
https://www.linkedin.com/pulse/configuration-management-system-vs-change-bsc-pmp-pmi-rmp-tot-
The guy has copied my content and posted there. I have filed a copyright infringement notice with LinkedIn.
Thanks Amit for letting me know.
Dear Fahad, Thanks for your great explanation, But I’m still little confused about the configuration management system.
Let’s take your instance ( Increasing the number of classrooms from 10 to 15), That’s great.
You said that any chang to the project processes or baseline is considered as a change management system, So in the previous instance ,when we decide to increase from 10 to 15 , I think this change affects directly the scope of the project, which is in turn one of the project baseline.
因此,我认为这将在变更管理系统之下。
Waiting for more information,and thanks in advance.
Change management is a subset of configuration management.
The change management plant defines the process for managing changes on the project.
The PMBOK Guide fifth edition, page: 138
This post is so useful. So Change Management Plan is a subset of Configuration Management Plan right. However if a question is asked – Change Management Plan contains what? The right answer would be Project Management Plan or Configuration Management Plan. And why?
谢谢in advance
很好地解释了最令人困惑的差异之一。
Thanks AG for stopping by and leaving your comment.
Ur site is excellent! Explanations/clarifications are awesome!!!! Downloaded your guides, hope they’re as useful!
感谢尖叫的评论。
Who will initiate or approve the change request. When we will raise change request and when we can update project without change request.
理解整个过程我建议你阅读the Integration Management Knowledge area from the PMBOK Guide.
BRAZIL,
CHANGE CONTROLS GO TO CCB CHANGE CONTROL BOARD TO APPROVE OR REJECT THE REQUESTS. IN SOME PROJECTS, THE SPONSOR GIVES SOME AUTHORITY TO THE PROJECT MANAGER TO APPROVE SOME CHANGE REQUESTS AND IT DEPENDS ON THE CONTRACT AND ROLES AND RESPONSIBILITIES.
Change management is a subset of configuration management.
Nice post Fahad!
In your one of the example in the blog. When client requested to increase the room numbers from 10 to 15. The Configuration Change is evident…Agreed!. But doesn’t a Change Request comes into picture, since adding more rooms would cause change in Project baseline i.e. Cost,schedule. E.g, work packages produced by taking 10 rooms into account… Kind of confused here. Please advise.
Thanks a lot for such easy to understand & simple explanation.
You are welcome Anusha.
You are welcome Ram.
Hi Fahad,
That’s an excellent explanation of Change Vs Configuration Management. Thanks for such wonderful comparison & vivid clarification.
To Summarize from the above,
1.更改管理是配置管理的子集
2. Change Management is applicable for Process/Baseline changes.
3. Configuration Management is applicable for Product changes & updated document repository.
4. Both undergoes integrated change control process.
Regards,
Ram Narayan
Thanks Fahad, I have passes PMP Exam last week with 4P & 1MP, in first attempt.
Thanks for all the support your blog have provided to me & all PMP aspirants.
恭喜ASIF通过PMP考试,我很高兴我能为您提供一些帮助。
Dear Fahad:
Your explanations are awesome for PMP aspirants, reference to this discussion, can you clarify in which PMI process Change management Plan &/if , Configuration Management Plan is developed , According to PMBOK -5????
谢谢,祝您好心...
In develop project management plan.
The PMBOK Guide page: 77
谢谢
You are welcome Aretit.
Brilliant explanation! Keep up the good work, Sir.
Thank You!
Thanks Janak.
Did PMI answered your question?
Thanks
No, I did not receive the reply from the PMI.
I just luv the way you make things simpler.
Amazing job.
谢谢, kindly
Thanks Sarika for your comment.
感谢你的博客信息rmation. It helped me lot. Thanks.
Abhijeet感谢你的评论。
Crystal clear explanation of this subject matter. Thank you very much!!!!
不客气迈克尔。
Are Configuration Management and Change Management differing from Configuration control and change control?
In the PMBOX Guide fifth ed. Says: Configuration control is focused on the specification of both the deliverables and the process while you mentioned In the Configuration Management System, changes related to product specification are managed.
谢谢.
Please refer page 532, the PMBOK Guide 5th edition.
Dear Fahad,
Your work is impressive. But could you clarify Saad’s doubt? I share it too.
Documenting changes in scope/configuration of the product (deliverable) is configuration management
Documenting change in processes/cost baseline/schedule baseline is change management.
Is this understanding correct? If yes, pg. 96 of PMBOK 5th ed. says “Configuration control is focused on the specification of both the deliverables and the process “. How come configuration control is focused on specification of the process? This is description of change control right?
I feel there is some discrepancy between the definition of configuration management mentioned in these two places.
Anyway, I’m going to write a mail to PMI, let’s us see their reply.
Yes we should. Kindly update us.
To my understanding, the configuration management affects both, the product and process where as change management only affects the process.
When a change to a product specification is managed (configuration), it “may” incorporate change to schedule and/ or cost as well. Both have to go through same Integrated Change Control, affecting either only to the product specification OR project process OR both. Though not particularly mentioned in PMBOK, I assume, while change management may act alone, the configuration management has to take change management along, may be as a subset or as an accompanying document.
Please correct me, if I am missing/ deviating.
I have written to PMI. I hope they will reply within this week.
Tauseef, I agree with your assessment: “Change management may act alone, [but] the configuration management has to take change management along”.
Also based on how PMBOK 5.6.1.1 – Control Scope describes Configuration Management Plan, it seems the plan itself defines what specifically *is* configurable (and therefore, in which cases the configuration control is applicable).
I only happened across this blog because one of my PMP Certification Exam Prep study questions asserted that Configuration Management “does NOT take the place of a Change Management System, but rather works with it”.
你好,
请您告诉我什么之间有什么不同:
Change management plan & change management system
Also configuration management plan & configuration management system
谢谢very much
Imad
Basically you are asking the difference between plan and system.
Plan is something documented which guides you in your act. System is something that helps you implementing your plan.
Hope it helps.
Can we say: configuration management will include change management but the change management will not include configuration management.
In other words: If we back to the building school example:
1- When client change form 10 to 15 classes: We should do configuration management and change management.
2- When project schedule will delay one week: We should change management.
Configuration management and change management are different to each other.据我了解,在配置MGMT中,我们根据Change MGMT批准的变更顺序或变化顺序进行了相应的自定义。
You can say that the change management is a subset of the configuration management.
Thanks for grate emample
谢谢Vara for your comment!
Hi Fahad,
Does both configuration & change management have to be done through the integrated change control process and also will this directly affect the project management plan ?
Yes, they have to be done through the integrated change control process. It may or may not affect the project management plan.
Thnks Fahad.
Hi Fahad
I read your post about change management and configuration management . I still have some concerned about all this term.
Configuration management and change management system
Change management plan and change control system
Can someone gives me more explanation and difference between these four terms with example it would be nice
Thanks in advance for you contribution to my understanding
best regard
Well come to the world of PMP Sathish and God luck for you professional carrer bro
Hi Fahad,
我通过了考试。感谢你的博客信息rmation. It helped me lot. Thanks.
Congratulation Sathish!
Useful one and clarified my doubts with your example.
Regards
Pullikol
You’re welcome Pullikol…
非常感谢Fahad
Hi Shariff,
Excellent explanation with good example. Thanks. Can you also explain different between change management system and configuration management system.
Hi Thathish,
我的理解,配置和变化management systems are component of the organisation project management information system. However, the configuration management system consists of documented procedures employ in identifying, documenting and controlling changes to functional and physical characteristics of a product, service and results, including tracking system and approval level. On the other hand, a change management system defines how project deliverables and documentation is controlled, changed and approved. The latter is usually a subset of the former. See PMBOK Guide page 428-429.
I hope this clarification helps.
hi shariff,
configuration management system is from pmis but i think and i could be wrong change control is from opa. another question is change management the same as change control. thanks.
Fahad,
您对变更和配置管理之间差异的解释是有效的。我想补充一点,配置管理还包括管理文档的更改(使项目团队知道哪个版本是当前的)以及在此工作中采用的组织工具。
Regards,
Shariff
Awesome. Thanks a lot for your amazing explanation
不客气。
Dear Fahad,
Keep on explaining the things like your way!!
感谢您的评论Ritesh。
Excellent Clarifications…. Difficult to forget now…Thanks…
You’re welcome.
But in some questions asked where would you go to find a document, the answer is config management. seems its considered as a document management repository tool also, right ?
它在那里谈论了这些文档的最新版本……当有批准的更改请求时,我们对基线进行了更改。
Hello Shweta,
Did Sangeetha give you the answer? If not, then could you be little more specific?
Hi Fahad,
Can we say Configuration management is scope change and change management is shcedule change?
Thanks
Ramesh
Configuration management is scope change – Yes, we can say this.
And Change Management includes the change in schedule and cost baselines.
i dont think so because changing scope will add a new scope and new related spécification. but configuration is concerned by changing spécifications to an existing scope. so i think changing scope is concerned with change management system and not configuration management system
Yes, you are right, if there is change in product scope then we can say it will be managed through the configuration change management system.
As Nedhir said, if there is scope change, it should be considered as change management. Like the school example, if the color of the classroom is changed from green to yellow, then this should configuration change
hi Fahad,
thanks for spreading the knowledge. why configuration management system belongs to EEF and the change control belongs to OPA and they are both related. thanks.
hi fahad,
i found this video which explain the difference between the two:
Change Management vs. Configuration Management – PMP Exam Prep
https://www.youtube.com/watch?v=VErsnGIqzEQ
Thanks for sharing Michael.
good
Thanks Aretit.