Configuration Management vs Change Management

July 2, 2021
法哈德·乌斯曼尼(Fahad Usmani), PMP
configuration management vs change management

Project environments are dynamic, and changes are constant in areas like process, planning, or scope. You can group these changes into two categories:

  1. Change Management
  2. Configuration Management

“Change Management” is the first category. Here you manage changes related to project management plans, processes, and baselines.

In the second category, you manage changes related toproduct scope, known as configuration management.

Change requests are required when baselines are established, and you have to make changes to them. If the baselines are not set, no formal change request is required. Change requests and configuration requests are part of the integration management system.

变更管理是项目管理中的著名术语,但配置管理不是。在IT领域,经常使用“配置管理”一词,因此,如果您不在这个行业中,则可能会面临理解该概念的问题。

As a non-IT professional, I had this struggle. However, now that I have passed the PMP and PMI-RMP exams, I can help you understand the concepts in this blog post.

Please note that change management and configuration management are the most important concepts for thePMP exam, and you are going to see many questions on them.

Change Management System

According to the PMBOK Guide 6th edition, “Change Control is focused on identifying, documenting and controlling changes tothe project和项目基线。”

In the change management system, you manage the changes related to the project scope, planning, and baselines.

For example, you run out of money and you need additional funding to complete the project, therefore, you will raise a change request for additional funds. Or, you may not be able to complete your project within the specified time and require a time extension.

In the change management system, the change request is analyzed for any possible impact on any other project objectives. Afterward, the request is either approved or rejected.

To minimize disruption, a change management system must ensure that all parameters are identified and analyzed for any possible impact.

If the change request is approved, you will update the concerned baseline, update the project documents, and inform the concerned stakeholders.

Change Management Activities

您在变更管理期间进行以下操作:

  1. Identify the changes.
  2. Prepare proper documentation for the changes.
  3. Review, analyze, and make a decision for the change request.
  4. 确保请求已实施,注册和传达。

Configuration Management System

According to the PMBOK Guide 6th edition, “Configuration Control focuses on the specifications of both the deliverables and the processes.”

In the configuration management system, you manage the changes related to the product specification and the process.

For example, suppose you are developing a product and the client requests the addition of some extra features.

由于此更改与产品的配置有关,因此您将使用配置管理系统处理此更改。

Configuration management documents how you will monitor and control changes. It is a process of defining configurable items (product, service, result, and component) and controlling changes to such items.

The configuration management plan keeps version control of the product. Here you can keep a log of all the changes made to any version of the product for review.

Configuration Management Activities

您在配置管理期间进行以下操作:

  1. Identify the configurable items.
  2. Record and prepare a report for all configurable items.
  3. Verify and conduct an audit of all configurations are as per the requirements.

A Real World Example of Change and Configuration Management

Suppose you are working on a project to construct a school building with ten classrooms.

Case: 1

During the middle of the project, your contractor for steelwork walks off the job and you have to find a replacement. You find an alternative, but the new contractor will not start working on your project for a week.

This will delay the project. Therefore, you will raise a change request for a one-week extension of the schedule through the change management system.

Once this request is approved, you will update your schedule baseline.

这是变更管理系统的一个示例。

现在,让我们查看配置管理系统的示例。

Case: 2

You are constructing a school building, and the client requests that you increase the number of rooms from ten to fifteen.

This is a request to change the product scope as the client has altered the product configuration.

You will handle this change under the configuration management system because here the specifications of your product have changed. Earlier, the school building had ten rooms, and now it will have fifteen rooms.

请注意,在第一种情况下,你提高了change request to increase the deadline of the project by one week. There was no change to the product, the change was only needed in the schedule baseline; the school building was the same, but you will hand over this building to the client one week later.

The Difference Between Change Management and Configuration Management Systems

The main difference between the change management and configuration management systems is that change management deals with processes, plans, and baselines, while configuration management deals with product specifications.

An example of a change management system can be additional funding requirements or a schedule extension, while an example of configuration management can be an extra feature added to the product.

Conditions for Change Management

以下是变更管理的一些条件:

  • Delay in schedule: You will have to develop a new schedule reflecting the current situation.
  • Cost overrun: You will need to re-estimate your cost to complete the project.

配置管理条件

The following are a few conditions for configuration management:

  • Market competition forces new features on the product.
  • The project took so long that the product is obsolete, so an update is required.
  • The client requested you add some extra functions.
  • Due to cost overrun, some features are removed from the product.
  • To complete the project early, some features are removed.

Change Management Vs Configuration Management

变更管理和配置管理不会争夺相同的空间。它们用于不同的目的。

According to the PMBOK Guide 6th edition, “Configuration control is focused on the specification of both the deliverables and the processes, while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.”

产品配置的任何更改也会影响项目范围,您将更新项目计划,成本和计划基准。

Configuration management has a larger scope than change management.

Who Can Raise a Change and Configuration Request and Who Can Authorize It?

Anyone can raise a change request but it must be approved by the project manager or a higher authority, as mentioned in the configuration or change management plan. If the client is not involved in the process, their consent is required to implement the change request.

更高的权力可以是项目管理计划中提到的变更控制委员会(CCB),项目管理办公室(PMO)或任何其他利益相关者。

Regarding a configuration request, usually, it comes from the client as it involves a change in the product.

This request is reviewed by the project manager and then forwarded to the concerned higher authority for their review and approval. An agreement from the client may be required because they have to pay for any additional features.

Summary

变更管理和配置管理是集成管理的一部分,并且都涉及项目或产品中可能发生的所有更改。变更管理与与计划,过程和基准相关的更改有关,而配置管理涉及与产品范围相关的更改。项目经理的工作是提出这些请求,并确保对它们进行适当的审查。一旦做出决定,应立即实施。

Now I hope you will not have any problem in solving questions on the PMP exam regarding change management and configuration management systems.

您如何管理项目的更改?请通过评论部分分享您的经验。

PMP Question Bank

This is the most popular Question Bank for the PMP Exam. To date, this PMP Question Bank has helped over 10,000 PMP aspirants pass the PMP exam.

PMP公式指南

This is the most popular Formula Guide for the PMP Exam. If you face difficulty with attempting mathematical questions for the PMP exam.



推荐阅读


把你的想法说出来

  • Hello Fahad,
    Thank you for your well thought out article.

    我喜欢您的定义,看起来正确;当然,解释PMBOK的一种方法。但是,问题的一部分(以及为什么您写了这篇文章以及像我这样的人以及其他读者寻求澄清的人),PMBOK非常使它成为一笔模糊的交易。您的定义很好,很有意义,这也是我所拥护的:配置与产品有关;变化与项目文档,基准,流程等有关,但是存在矛盾。
    And, as I’ve tried to make sense of it in my own head in studying PMBOK (as you know PMI has “THEIR definition” of things, not always the same as “Organization/Company lambda’s”), there are some contradictions in PMBOK, and thus in your own definitions above—which are indeed direct out of PMBOK. You say that “Change Control” is about “Project stuff” — Project Documents, Baselines and Processes ; and “Configuration Control” as Product/Scope related (“Product Stuff”). Yet, you then correctly quote PMBOK that ““Configuration Control focuses on the specifications of both the deliverables and the processes” (i.e., note PROCESSES).
    此外,当您引用PMBOK时,您再次指出矛盾:“配置控件专注于可交付成果和流程的规范(即注释过程!),而更改控制则集中于识别,记录和批准或批准或批准或拒绝对项目文档,可交付成果或基准的更改”(注释可交付物!)。因此,不符合您所陈述的解释 /省。

    Another interpretation (that I’ve enountered) is that Change Control is the process of changing Project “Artifacts” (Project document, plans, process, deliverables, baselines – in short, everything that is under control): the written change requests, the Change Control Board, voting, approval / rejections, etc. And that Configuration control is the versioning, identification of “current version”, archiving of old versions, etc. of all “Project Artifacts” (Artifacts covering both “Project Stuff” like docs & processes and “Product Stuff”, like deliverables). This is the one espoused by Rita Mulcahey (her PM book). This interpretation also has problems and contradictions with some of the same definitions (and others) of Change Control (and Change Mgmt) and Configuration Control (and Config Mgmt) that is found in PMBOK.
    所有这么说:PMBOK由许多人撰写,然后在其各种作者和章节上“控制”以确保整体完整性。但是仍然存在不陈述和矛盾 - 我相信这是一个。他们似乎用新版本的PMBOK清除了这些,但其他版本出现了。所有这些都说,您的定义是一个很好的定义 - 我一直认为是真实的。现在我开始怀疑。阅读并现在研究PMBOK,因此试图理解“ PMBOK如何定义此问题”,因为如前所述,PMBOK的定义并不总是同一个人的“现实世界”定义。没关系,他们还不清楚,他们的方法中存在矛盾。谢谢。很棒的文章。如果您可以或可以与他们对话 - 告诉PMI澄清他们的定义! Look forward to your feedback.

  • Change Management” is the first category. Here you manage changes related to project management plans, {processes}, and baselines.

    According to the PMBOK Guide 6th edition, “Configuration Control focuses on the specifications of both the deliverables and the {processes}.”

    I don’t understand how the 2 terms dealing with{ process }
    kindly clarify it.

  • 嗨,法哈德先生,
    Now, if the client request change in my scope,
    I need to go with Change management and configuration management in parallel

    • Hello Anas,

      I believe he is asking for change in product scope. In this case, you will go for configuration management.

      • Hi Fahad,

        更改产品范围,不需要更改时间表和成本基线吗?随着产品范围的增加,成本和时间的增加。然后,我们必须对两个配置管理进行处理,然后进行变更管理,不是吗?

  • Does the Configuration Management, lead to raise a Change request in Project Management ?

    Below are same 2 examples used in here, to help you understand, what I am trying to convey.

    示例1
    During the middle of the project, my contractor for steel work walks off the job and I have to find a replacement. I found an alternative, but the new contractor will not start working on the project for a week.

    This will delay the project. Therefore, I will raise a change request for a one-week extension of the schedule through the change management system.

    示例2
    现在,我正在建造一座学校建筑物,客户要求我必须将房间数量从10到15增加。

    This is a request to change the product scope as the client has altered the product configuration.

    I will handle this change under the configuration management system because here the specifications of the product have changed. Earlier the school building had ten rooms, and now it will have fifteen rooms.

    However, building additional 5 rooms will take more time than building 10 rooms, planned earlier. Hence, my schedule will also change as a result effecting my baseline, and so I have to raise a change request.

    Please let me know if my understanding is correct !

    • Hello Mahfuz,

      In the PMP Question Bank you will find 400 Questions. The PMP Mock Test has 200 questions.

  • ASC Fahad, thanks in million Brother for your great and Briliant mind for providing us this wealthy knowledge,

  • This article is very good. It helps me to get clear about Configuration management and Change Request.

    因此,我想确认我们的项目。

    My project is to build the Window with blue color. But in executing, The window was painted with blue color. After that the stakeholder changed the color to yellow.

    So, this should be managed by Change management or Configuration Management.
    Because it impacts to schedule, cost and product specification.

    Please explain.

    太感谢了。

  • Hello Fahad,

    Please Read this sections from the PMBOK® Guide Sixth Edition, and then correct your answer and please also try to understand it well. What you are saying about configuration management and change management isn’t True at all.

    “Configuration management plan:
    Describes how the information about the items of the project (and which items) will be recorded and updated so that the product, service, or result of the project remains consistent and/or operative.

    “一旦可交付的第一个版本完成,应应用变更控制。配置管理工具和过程支持了可交付的多个版本或版本(例如文档,软件和构建块)的控制。”

    “Before the baselines are established, changes are not required to be formally controlled by the Perform Integrated Change Control process. Once the project is baselined, change requests go through this process. As a general rule, each project’s configuration management plan should define which project artifacts need to be placed under configuration control. Any change in a configuration element should be formally controlled and will require a change request.”

    “Configuration management activities such as: how changes will be initiated; how impacts will be analyzed; how they will be traced, tracked, and reported; as well as the authorization levels required to approve these changes;”

    Thank you.

    • 您好Shady,尽管可以将更多的技术细节添加到此博客文章中,但此处讨论的观点是有效的。

  • Hi Fahad, i also have same question above that why change management is a subset of configuration management instead another way around. Is there any reasoning behind?
    Also have another question which made me confuse,
    Ques: project manager doing quality check for steel bolts of 20 cm. The acceptable control limits are 19.955 cm and 20.045 cm. The measurements made at the end of the process yielded the following results : 20.033 cm, 19.982 cm, 19,995 cm, 20.006 cm, 19.970 cm, 19.968 cm, 19.963 cm, 19.958 cm, 19.962 cm, 19.979 cm and 19.959 cm. What should be done?

    I always think if control limits are good why we need to frther investigate the process? Is it not control limits are typically similar like tolerances (except prior is defined by PM and later by customer.)

    Thanks
    Sumit

    • Configuration management has larger scope as compared to change management.

      Control limits are set by project manager to control the process and if anything goes outside of it, he will check if everything is right though the project is within acceptable range.

      • 在我看来,配置的变化也可能影响成本,计划基线;或可能会引起一些风险。在这种情况下,需要根据影响来启动管理。因此,更改管理可以是配置的子集。

        Please share your thoughts about my views .

  • Can you explain why the change management system is a subset of the configuration management system?
    While opposite can be true but how change management system falls under configuration management system.

  • 法赫德感谢你的解释,但是一个问题, according to your explanation, configuration is mainly for product and change is mainly focus on baseline and project plans, so i see that at many points they will be meet together, like for scenario 2 when u need to change the number of classrooms from 10 to 20 now yes that change in the product, but to meet that product you will need to change the plans as well, so in that scenario we will pass by both configuration and change, correct me if im wrong

    Thanks again

  • Any changes in the project management plans and all its subsidiary plans and baselines requires to be updated through change control process and have it approved. Then do all project documents would need to go through the change control process before updates can be made? e.g. stake holder register or risk register or requirement documents. Can these by updated without going through a formal change control process and approval? Can the PM make the changes without some else’s approval?

    • These are the project document and supposed to be updated all the time throughout the project lifecycle. They do not require to go through this process.

      • 那么所有项目文件是否都以相同的方式处理?PMBOK指南第78页中还有一系列文档清单。除了绩效数据和问题/更改日志bob手机客户端/预测等明显的文档外,所有其他文档都可以在未经正式更改控制批准的情况下进行更新吗?

  • Thanks so much Fahad for this piece, it brings simplicity and gives clarity to differentiate between Configuration and Change Management System.

  • Dear
    Thank you very murch for the nice explanition.
    Really I like it specially that I am starting the course of PMP preparation for the PMP exam.
    Thanks and regalrds.
    Abdulmohsen

  • I don’t agree this clarification, PMBOK does not very clearly distinct the two, my impression is that configuration management is super set of change manamement, plus some document record repository functions.

  • can we say that change in spécifications (configurations) can be similar to change to product quality attributes? what is the difference between both of them? please i need clarification
    thanks in advance !

  • 我认为配置管理基本上是如何will you manage the ‘integrity’ of your products/artifacts, how will all the stakeholders know what’s the latest blueprint to reference, what’s the latest architecture diagram, what’s the latest design document, what’s the latest source code to act one, etc.
    The Change Management is just any changes, even the ones which doesn’t result in any change to Scope, Cost, Schedule.

      • Configuration management system is the system defining what your final product look like in specific and technical details.
        Change control system: the set of procedures and processes that you need to apply in order to make a change

    • The guy has copied my content and posted there. I have filed a copyright infringement notice with LinkedIn.

      感谢阿米特让我知道。

  • Dear Fahad, Thanks for your great explanation, But I’m still little confused about the configuration management system.
    Let’s take your instance ( Increasing the number of classrooms from 10 to 15), That’s great.
    你说任何chang o项目流程r baseline is considered as a change management system, So in the previous instance ,when we decide to increase from 10 to 15 , I think this change affects directly the scope of the project, which is in turn one of the project baseline.
    So, in my opinion, this will be under the change management system.
    Waiting for more information,and thanks in advance.

  • The change management plant defines the process for managing changes on the project.

    PMBObob手机客户端K指南第五版,第138页

  • This post is so useful. So Change Management Plan is a subset of Configuration Management Plan right. However if a question is asked – Change Management Plan contains what? The right answer would be Project Management Plan or Configuration Management Plan. And why?

    Thank you in advance

  • Who will initiate or approve the change request. When we will raise change request and when we can update project without change request.

    • 理解整个过程我建议你阅读the Integration Management Knowledge area from the PMBOK Guide.

    • 巴西,

      CHANGE CONTROLS GO TO CCB CHANGE CONTROL BOARD TO APPROVE OR REJECT THE REQUESTS. IN SOME PROJECTS, THE SPONSOR GIVES SOME AUTHORITY TO THE PROJECT MANAGER TO APPROVE SOME CHANGE REQUESTS AND IT DEPENDS ON THE CONTRACT AND ROLES AND RESPONSIBILITIES.

  • 不错的帖子法哈德!

    In your one of the example in the blog. When client requested to increase the room numbers from 10 to 15. The Configuration Change is evident…Agreed!. But doesn’t a Change Request comes into picture, since adding more rooms would cause change in Project baseline i.e. Cost,schedule. E.g, work packages produced by taking 10 rooms into account… Kind of confused here. Please advise.

  • Hi Fahad,

    That’s an excellent explanation of Change Vs Configuration Management. Thanks for such wonderful comparison & vivid clarification.

    总结以上,

    1. Change Management is the Subset of Configuration Management
    2.更改管理适用于过程/基线更改。
    3. Configuration Management is applicable for Product changes & updated document repository.
    4. Both undergoes integrated change control process.

    Regards,
    拉姆·纳拉扬(Ram Narayan)

  • Thanks Fahad, I have passes PMP Exam last week with 4P & 1MP, in first attempt.

    Thanks for all the support your blog have provided to me & all PMP aspirants.

    • Congratulations Asif for passing the PMP exam and I am glad that I could be of some help to you.

  • Dear Fahad:

    您的解释对于PMP有抱负的人来说很棒,参考此讨论,您是否可以澄清PMI流程更改管理计划和/如果制定了配置管理计划,请根据PMBOK -5?

    Thanks & best wishes…

  • Are Configuration Management and Change Management differing from Configuration control and change control?

    In the PMBOX Guide fifth ed. Says: Configuration control is focused on the specification of both the deliverables and the process while you mentioned In the Configuration Management System, changes related to product specification are managed.

    Thank you.

      • Dear Fahad,

        您的工作令人印象深刻。但是您能澄清萨德的疑问吗?我也分享。

        Documenting changes in scope/configuration of the product (deliverable) is configuration management

        Documenting change in processes/cost baseline/schedule baseline is change management.

        Is this understanding correct? If yes, pg. 96 of PMBOK 5th ed. says “Configuration control is focused on the specification of both the deliverables and the process “. How come configuration control is focused on specification of the process? This is description of change control right?

        • I feel there is some discrepancy between the definition of configuration management mentioned in these two places.

          Anyway, I’m going to write a mail to PMI, let’s us see their reply.

        • To my understanding, the configuration management affects both, the product and process where as change management only affects the process.

          When a change to a product specification is managed (configuration), it “may” incorporate change to schedule and/ or cost as well. Both have to go through same Integrated Change Control, affecting either only to the product specification OR project process OR both. Though not particularly mentioned in PMBOK, I assume, while change management may act alone, the configuration management has to take change management along, may be as a subset or as an accompanying document.

          Please correct me, if I am missing/ deviating.

          • Tauseef, I agree with your assessment: “Change management may act alone, [but] the configuration management has to take change management along”.

            同样,基于PMBOK 5.6.1.1 - 控制范围描述了配置管理计划,该计划本身似乎定义了 *可构型 *的特殊性(因此,在哪种情况下,配置控件适用)。

            I only happened across this blog because one of my PMP Certification Exam Prep study questions asserted that Configuration Management “does NOT take the place of a Change Management System, but rather works with it”.

  • Hi,
    Please can you tell me what is different between :
    Change management plan & change management system
    Also configuration management plan & configuration management system
    Thank you very much
    Imad

    • Basically you are asking the difference between plan and system.

      Plan is something documented which guides you in your act. System is something that helps you implementing your plan.

      Hope it helps.

  • 我们可以说:配置管理将包括更改管理,但更改管理将不包括配置管理。

    换句话说:如果我们回到建筑学校的例子:
    1- When client change form 10 to 15 classes: We should do configuration management and change management.
    2-当项目时间表延迟一周时:我们应该更改管理。

      • From what I understand, in configuration mgmt we customize accordingly to the change order or variation order that have been approved by change mgmt.

        • You can say that the change management is a subset of the configuration management.

  • Hi Fahad,

    Does both configuration & change management have to be done through the integrated change control process and also will this directly affect the project management plan ?

  • Hi Fahad
    我阅读了您有关变更管理和配置管理的帖子。我仍然对所有这个术语感到担忧。
    配置管理和变更管理系统
    Change management plan and change control system

    Can someone gives me more explanation and difference between these four terms with example it would be nice
    Thanks in advance for you contribution to my understanding

    best regard

  • Hi Shariff,

    出色的解释,有很好的例子。谢谢。您还可以解释变更管理系统和配置管理系统之间的不同。

    • Hi Thathish,

      我的理解,配置和变化management systems are component of the organisation project management information system. However, the configuration management system consists of documented procedures employ in identifying, documenting and controlling changes to functional and physical characteristics of a product, service and results, including tracking system and approval level. On the other hand, a change management system defines how project deliverables and documentation is controlled, changed and approved. The latter is usually a subset of the former. See PMBOK Guide page 428-429.

      I hope this clarification helps.

      • hi shariff,
        configuration management system is from pmis but i think and i could be wrong change control is from opa. another question is change management the same as change control. thanks.

  • Fahad,

    Your explanation about the difference between change and configuration management is valid. I would like to add that Configuration Management also includes managing changes to the documentations ( to enable the project team know which version is current) and the organisation tool employed in this effort.

    Regards,

    Shariff

  • But in some questions asked where would you go to find a document, the answer is config management. seems its considered as a document management repository tool also, right ?

    • There it talks about the latest version of the documents … Becoz we have changes to the baseline when there is an approved change request.

    • 你好shweta,

      Did Sangeetha give you the answer? If not, then could you be little more specific?

    • Configuration management is scope change – Yes, we can say this.

      And Change Management includes the change in schedule and cost baselines.

      • 我不这么认为,因为更改范围会增加新的范围和新的相关Spécification。但是,通过将Spécifications更改为现有范围来涉及配置。因此,我认为更改范围与变更管理系统有关,而不是配置管理系统

        • Yes, you are right, if there is change in product scope then we can say it will be managed through the configuration change management system.

          • As Nedhir said, if there is scope change, it should be considered as change management. Like the school example, if the color of the classroom is changed from green to yellow, then this should configuration change

      • hi Fahad,

        thanks for spreading the knowledge. why configuration management system belongs to EEF and the change control belongs to OPA and they are both related. thanks.

  • {“电子邮件”:“邮件地址无效”,“url”:”网站的广告dress invalid","required":"Required field missing"}

    Recommended Resources

    Use these resources for your PMP certification exam preparation and pass the exam with minimal effort.

    The PMP Training Program


    The PMI approved 35 contact hours training program that is 100% online, affordable, and help you prepare the PMP exam.

    The PMP Exam Preparation Tool


    PMP考试准备课程,即100%在线,为您提供通过PMP考试所需的一切。

    >