关闭采购与关闭项目c

现在,该博客文章已经过时了,因为《 PMBOK指南》第6版中没有密切的采购过程。bob手机客户端

起初,你可能认为秘密地e procurement process and close project process are synonyms of each other. I have seen people asking for clarification on them in severalPMPforums because they have many things in common. It can be difficult for students of project management to distinguish the two.

This blog post is meant to clear up these concepts. After reading this, you won’t have any problem differentiating between these processes.

Before we start discussing in detail, let’s make sure we all understand the key terms: procurement, phase, andproject

Procurement

采购可以定义为从外部来源收购商品,服务或工作。

简而言之,您将项目工作的一部分分包给外部承包商。这是出于多种原因进行的。例如,如果您无法自行完成这项工作,或者是否将更具成本效益的外包。

Phase

According to thebob手机客户端,第五edition, “Project phase is a collection of logically related project activities that culminate in the completion of one or more deliverables.”

项目分为阶段的原因很多。The most important reason is project size. If you want to manage a large undertaking effectively, you have to divide it into phases and complete them in order, unless circumstances require phase overlap.

项目

根据PMBOK指南,第五版:“一个bob手机客户端项目是为创建独特的产品,服务或结果而进行的临时努力。”

换句话说,您可以说项目的性质是非永久性的,并且要产生一定的输出。实现目标时,项目关闭。

Now let’s look at the close procurement and close project processes.

亲密采购Process

In reference to the PMBOK Guide, fifth edition, “Close procurement is the process of completing each procurement.”

The close procurement process is also known as the contract closure. It supports the close project or close phase processes.

据说在达到合同截止日期并结束时或终止合同时,采购将关闭。

A project can have a single采购合同or multiple contracts.

近距离采购过程只会每次采购合同一次。但是,如果该项目有多个采购合同,则由于有很多合同,将多次执行近距离采购过程。

A project can be completed without any procurement contract, if it is not necessary for the project, there is no need for the close procurement process.

Close Project Process

根据《 PMBOK指南》第五版,“bob手机客户端关键项目或阶段是完成所有项目管理过程组中所有活动以正式完成项目或阶段的过程。”

This definition shows that the close project or close phase process is performed when the project or phase is finally completed and deliverables are accepted.

要完成关键项目或关闭阶段流程,必须完成关闭的采购过程;否则,前者将不会发生 - 否则,对于不必完成该项目即可完成近距离采购过程的近距离采购过程是不同的。

A Real-World Example

在这种情况下,让我们假设您有一个项目来建造一座学校建筑。

您发现,为了有效地完成项目,应通过采购合同进行一些工作,例如:

  • 地球发掘
  • 电气工作
  • 木工工作
  • Painting

You need to do some excavation before starting any construction activities. Therefore, you have to procure this job from a contractor and negotiate with them.

The contractor completes the job, you pay them for the work and you close this procurement contract. Afterward, you construct the building.

Now you are at the stage where it is time to install electrical systems in the building. You also have procured this task. The contractor comes and does their part, and you release them by paying the agreed amount of money, and you close the contract.

Afterward, carpentry and painting work starts. You also have procured these jobs. Once these contractors complete their tasks, you make payment and then you close these contracts as well.

该建筑物已经准备就绪,因此您致电客户来检查它。客户满意后,他们就接受建筑物,签署接受信,并释放所有待处理的付款。一旦获得付款,就可以更新学习的课程,并发布团队和资源。b0b体育app最后,您关闭项目。

因此,在此示例中很明显,密切的采购过程是多次执行的,但是在项目结束时,关闭项目仅执行一次。

一些关键点

Please note the following:

  • The close procurement process must happen before the close project or close phase process.
  • The close procurement process may occur many times during theproject’s life cycle,但是密切的项目过程将在项目结束时仅执行一次。
  • In the close project or close phase processes, the client accepts the deliverables.
  • 接近采购过程可能会或可能不会发生,但是即使终止,每个项目也必须通过密切的项目过程。
  • In close procurement, you close your deal with your contractor, and in the close project process your client closes the deal with you.

注意:每个项目都有五个过程组,这些过程组从启动和结束过程组开始。有趣的是,这两个过程组仅由两个过程组成,这使它们成为五个过程中最小的过程。这两个过程组占PMP检查的21%。

在研究这些小过程组的情况下,您可以在您的大约42个问题上回答PMP examination。I advise that you pay special attention to these process groups in order to score well on the exam.

Summary

The close procurement and close project processes may look similar to you. However, they are different and serve different purposes. The close procurement process belongs to the procurement knowledge area, and the close project process belongs to project integration management. The output of the close project process is the final product, service, or result. On the other hand, the output of the close procurement process is closed procurement.

如果您想在此博客文章上分享您的想法,则可以通过评论部分进行。