contingency plan vs fallback plan

This is one of those concepts that makes professionals scratch their heads. I was a victim of it myself. During my initial days ofPMP exam preparation, I had difficulty understanding the difference between the contingency plan and the fallback plan.

I used to think that the contingency plan was used to manage identified risks and the fallback plan was for unidentified risks. This was wrong. Contingency and fallback plans help manage identified risks.

However, since both plans are used to manage risks, you may wonder which you should follow if any identified risk occurs as both deals with identified risks?

Since I have passed the PMP and PMI-RMP exams and understand these concepts well, I am writing this blog post and hope after reading it you will be able to differentiate the contingency and fallback plan.

应急方案

Merriam-Webster defines the term “contingency” as “an event that may but is not certain to occur.”

A contingency is an event that may or may not occur. Therefore, we can say that the contingency plan deals with events that may or may not occur.

A contingency plan is a part of the project management plan; it describes every action that you will take if any identified risk occurs.

让我们看一个现实世界中的现实示例。

意外计划的真实示例

You are working on a construction project, and there is a risk that rain may fall during execution, which will damage any consumables lying out in the open.

因此,您制定了一个计划,说:“如果有降雨的迹象,所有消耗品将覆盖有塑料板。”您还补充说,雨水停止后,您将带风扇/真空泵清洁并干燥湿的消耗品。

This is a contingency plan for this risk event.

You can find many definitions of a contingency plan on the internet that may appear different to you, but they may be individually correct.

Below are two different explanations of the contingency plan.

  • Contingency plans are the plans that describe the specific actions that will be taken if an opportunity or a threat occurs.
  • 如果有足够的警告信号(风险触发),将执行应急响应策略。

If you examine these definitions, you will find that they are not different, just phrased differently.

后备计划

The fallback plan is a part of the project management plan and defines under which circumstances action has to be taken.

A fallback plan is implemented when the contingency plan fails or is not fully effective. It is a backup for the contingency plan. You can say that the fallback plan is generally made for residual risks.

A Real-World Example of Fallback Plan

让我们重新考虑上面给出的示例。

Suppose the rain continued to fall for a very long time, longer than expected, which causes damage to the consumables.

In this case, you will implement your fallback plan. It says that if the rain continues to fall for a very long time, causing consumables to be damaged and the contingency plan fails, you will reorder consumables from a pre-identified supplier.

这是后备计划的一个例子。

Before I go any further, let me share another example from my own experience.

I am using a third-party backup service to save data for my blog. I can use this backup in case my site crashes and myhosting providerdoes not have any backup.

This is my contingency plan.

Now, what would happen if my site got hacked, and at the same time my third-party backup service also went out of business? How would I restore my blog?

这是我的后备计划发挥作用的地方。为了使自己免于这样的灾难,我总是将博客的最新副本保留在计算机和Google驱动器上。

Now, if my blog is hacked and even the third party service fails, I can restore my blog from my backup stored on my computer or online storage.

The Difference Between the Contingency Plan and Fallback Plan

There is no difference between the contingency plan and the fallback plan; they complement each other. The fallback plan only comes into use when the contingency plan fails.

Similarities Between the Contingency Plan and Fallback Plan

这两个计划之间的相似之处如下:

  • 这两个计划都被称为风险响应。
  • Both plans are used to manage the identified risks.
  • Both plans utilize the应急储备用于实施。

Summary

The contingency and fallback plans are the backbone of yourrisk management planthat helps you manage identified risks. You will implement the contingency plan if any identified risk occurs, and when the contingency plan fails or seem ineffective, you will implement the fallback plan.

您将使用应急储备应用应急计划或后备计划,而不是管理储备,因为应急储备用于确定的风险。管理储备用于管理身份不明的风险。

I hope that now you understand these terms. However, if you still have some trouble, leave a comment below. I am ready to discuss.

从PMP和PMI-RMP考试的角度来看,应急计划和后备计划非常重要,因此请务必很好地理解此主题。