contingency plan vs fallback plan

这是使专业人士挠头的概念之一。我本人是它的受害者。在我最初的日子PMP考试准备,我很难理解应急计划与后备计划之间的区别。

我曾经认为应急计划被用于管理已确定的风险,而后备计划是出于身份不明的风险。这是错误的。应急和后备计划有助于管理确定的风险。

However, since both plans are used to manage risks, you may wonder which you should follow if any identified risk occurs as both deals with identified risks?

Since I have passed the PMP and PMI-RMP exams and understand these concepts well, I am writing this blog post and hope after reading it you will be able to differentiate the contingency and fallback plan.

Contingency Plan

Merriam-Webster defines the term “contingency” as “an event that may but is not certain to occur.”

A contingency is an event that may or may not occur. Therefore, we can say that the contingency plan deals with events that may or may not occur.

A contingency plan is a part of the project management plan; it describes every action that you will take if any identified risk occurs.

Let us look at a real-world example of a contingency plan.

A Real-World Example of Contingency Plan

您正在进行一个建设项目,并且有可能在执行过程中降雨可能会降低,这会损害公开露面的任何消耗品。

Therefore, you make a plan that says, “If there is an indication of rainfall, all consumables will be covered with a plastic sheet.” You further add that after the rain stops, you will bring a fan/vacuum pump to clean and dry the wet consumables.

这是此风险事件的应急计划。

You can find many definitions of a contingency plan on the internet that may appear different to you, but they may be individually correct.

Below are two different explanations of the contingency plan.

  • Contingency plans are the plans that describe the specific actions that will be taken if an opportunity or a threat occurs.
  • A contingency response strategy will be executed if there is a sufficient warning sign (risk trigger).

如果您检查这些定义,您会发现它们没有什么不同,只是以不同的方式措辞。

后备计划

The fallback plan is a part of the project management plan and defines under which circumstances action has to be taken.

A fallback plan is implemented when the contingency plan fails or is not fully effective. It is a backup for the contingency plan. You can say that the fallback plan is generally made for residual risks.

A Real-World Example of Fallback Plan

Let’s reconsider the example given above.

Suppose the rain continued to fall for a very long time, longer than expected, which causes damage to the consumables.

In this case, you will implement your fallback plan. It says that if the rain continues to fall for a very long time, causing consumables to be damaged and the contingency plan fails, you will reorder consumables from a pre-identified supplier.

This is an example of a fallback plan.

在进一步之前,让我根据自己的经验分享另一个例子。

I am using a third-party backup service to save data for my blog. I can use this backup in case my site crashes and myhosting providerdoes not have any backup.

This is my contingency plan.

Now, what would happen if my site got hacked, and at the same time my third-party backup service also went out of business? How would I restore my blog?

This is where my fallback plan comes into play. To save myself from such a disaster, I always keep an updated copy of my blog on my computer and Google Drive.

Now, if my blog is hacked and even the third party service fails, I can restore my blog from my backup stored on my computer or online storage.

应急计划和后备计划之间的区别

There is no difference between the contingency plan and the fallback plan; they complement each other. The fallback plan only comes into use when the contingency plan fails.

应急计划与后备计划之间的相似之处

The similarities between these two plans are as follows:

  • Both plans are known as risk responses.
  • Both plans are used to manage the identified risks.
  • Both plans utilize thecontingency reserve为实现。

概括

The contingency and fallback plans are the backbone of yourrisk management plan这可以帮助您管理确定的风险。如果发生任何已确定的风险,您将实施应急计划,并且当应急计划失败或看起来无效时,您将实施后备计划。

You will use the contingency reserve to apply the contingency or fallback plan, not the management reserve because the contingency reserve is used for identified risks. The management reserve is used to manage unidentified risks.

I hope that now you understand these terms. However, if you still have some trouble, leave a comment below. I am ready to discuss.

The contingency plan and fallback plan are very important from a PMP and PMI-RMP exam point of view, so be sure to understand this topic well.

Fahad Usmani, PMP

I am Mohammad Fahad Usmani, B.E. PMP, PMI-RMP. I have been blogging on project management topics since 2011. To date, thousands of professionals have passed the PMP exam using my resources.