Risks occur in every project and as a project manager, it is your responsibility to manage them as they occur. These risks can be identified or unidentified. If these risks are identified, you will implement the contingency plan; otherwise, you will manage them through aworkaround。
来manage these risks, you will use the contingency reserve and management reserve. These reserves are defined during therisk management planningprocess. The contingency reserve and management reserve provide you with a cushion against the risks and are part of your project budget.
Many professionals assume these reserves are the same since they serve the same purpose. Generally, small and medium-sized organizations do not differentiate between them and take them as a percentage of the project cost to keep things simple. Therefore, professionals that have experience with theseorganizationsmay not know the difference between contingency and management reserves.
Contingency Reserve
You manage identified risks with the contingency reserve. This reserve can be in either cost or time.
The contingency reserve is not random; it is an estimated reserve based on various risk management techniques.
Project managers control this reserve; they have full authority to use it whenever an identified risk occurs. They can also delegate this authority to a risk owner. The risk owner will manage it and update the project manager in later stages.
How to Calculate the Contingency Reserve
有各种各样的技术来计算体积ingency reserve. Some of them are as follows:
- Percentage of the Project’s Cost
- Expected Monetary Value
- 决策树分析
- Monte Carlo Simulation
现在,我们将详细讨论每种技术。
Percentage of the Project’s Cost
Small and medium-sized organizations use this technique for small projects; it helps save money and resources.
Basically, you take a percentage of the cost of the project to calculate the contingency reserve, which usually lies between 3% and 10%. This number is based mainly on the perceived risk of the project.
Expected Monetary Value
Expected monetary valueis a statistical technique used to quantify risks and help calculate the contingency reserve. This technique is used in medium to high-cost projects, where the stakes are too high to risk the project failing.
首先,要找到预期的货币价值,您将计算每个事件的概率和影响,然后将它们倍增以生成每个风险的EMV。
Expected Monetary Value (EMV) = Probability * Impact
Then add the calculated EMV of all identified risks together.
Example
假设您有四个具有概率和影响的风险:
From the above table, you could argue that the funds needed to manage all identified risks is 4,500 USD, but this would be incorrect.
Not allpossible risksare guaranteed; some may happen and some may not. All risks will add their EMV to the pool. The risks that do occur will use money from the pool, but the risks that do not occur will help cover the cost of those that did.
In the above scenario, you may need to add 1,100 USD to your budget to cover all identified risks.
当您有很多风险时,预期的货币价值概念效果很好,因为您可以识别的越多,储备的传播就越好。如果您确定风险较少,则不会有足够的差异,并且储备可能会枯竭。
The EMV technique has a few drawbacks, which include:
- You assume that all risks are independent, which is not always the case.
- If the number of risks is small, the spread will be less, and the reserve may be insufficient.
- There is a chance of avoiding positive risks, which may lead to a false result.
决策树分析
Decision tree analysis is a quantitative risk analysis technique. This technique helps you select the best choice. This is a graphical technique that looks like a tree, hence its name.
在这里,您确定每个事件的预期货币价值,然后选择最佳选择。
Example:
Calculate the expected monetary value of the best choice.
In this example, you have three choices: Choice A, Choice B, and Choice C.
从上面的图中,所有三个选择represent opportunities. Therefore, you will find the expected monetary value of the three events and go with the most favorable. You are trying to get the maximum profit.
现在,让我们计算所有三个事件的EMV。
In the diagram, you were given the probability of one event, while the probability of the other event is not provided. To find the other probability, you have to subtract the probability of the first event from 100, because the sum of all possible outcomes for one event is 100%.
EMV of Choice A = 0.30*200 + 0.70*400
= 60 + 280
= 340 USD
选择的EMV b = 0.40*300 + 0.60*200
= 120 + 120
= 240 USD
选择的EMV C = 0.2*500 + 0.80*200
= 100 + 160
= 260 USD
您必须选择具有最高EMV的那个,即选择A。
Note that if all risks are negative, you select the least negative option. This is because you want to spend the least amount of money on managing risks.
Monte Carlo Simulation
In 1940, an atomic nuclear scientist named Stanislaw Ulam invented this technique and named it Monte Carlo after the city in Monaco, which is famous for its casinos.
This technique gives several possibilities of outcomes and the probabilities for any choice of action.
例如,我们将讨论Monte Carlo simulationin analyzing a project schedule. To use this technique, you must have duration estimates for each activity.
You have three activities with the following estimates (in months):
根据PERTestimate, these three activities will end in 18.3 months.
最好的情况是,这将需要15个月,在最坏的情况下,可能需要23个月。
Now, if we run the Monte Carlo simulation for these tasks, five hundred times, it will show us results like this:
(The above information is only for illustration purposes and is not from an actual Monte Carlo simulation test result.)
在审查了结果后,您可以确定有2%的机会在16个月内完成该项目,或者有70%的机会在19个月内完成该项目,或者有95%的机会在20个月内完成该项目等等。。
Likewise, you can run the Monte Carlo simulation for the budget.
例如,您可以生成数据,例如在项目成本中增加20,000美元,使您可以在预算内完成该项目的机会70%。如果您向项目成本增加40,000美元,则有95%的机会可以在预算内完成该项目,等等。
So, it’s clear that with the use of this technique you can get valuable information that will help you make better-informed decisions.
As you proceed, you will become more familiar with the situation and you can review this contingency reserve again. If required, this reserve can be reduced and you can release the funds.
Management Reserve
The management reserve is defined as the cost or time reserve that is used to manage the unidentified risks or “unknown-unknown”.
The management reserve is a part of the project budget but not the cost baseline. It is not an estimated reserve; it is a figure that is fashioned according to the organization’s policies.
It can be 5% of the total project cost or duration of the project or it may be as high as 10%. The management reserve is usually estimated based on the uncertainty of the project.
For example, if you are doing a project in which your organization has the expertise and experience, the management reserve will be less. In this case, there is less uncertainty.
However, if you are doing a kind of project new to your organization, the management reserve will be high, because, in this situation, the uncertainty is greater.
The project manager does not control management reserve, the management does. Therefore, the project manager must receive approval to use this reserve whenever any unidentified risk occurs.
Many organizations try to avoid using the management reserve. They think if the project manager has to come to them every time to get approval, then why keep it separate? The project manager can come any time they need extra money; so why have a management reserve?
On the PMP exam, you will see many questions on contingency reserve, management reserve, cost estimate, and the project budget. These are crucial concepts; without these reserves, you cannot estimate the cost baseline and project budget. Therefore, for your easy reference, I am explaining these topics here as well.
Cost Estimate
成本估算是所有人的成本work packagesand is “rolled up” to the top level; this is the total cost of the project.
Cost Baseline
When you add the contingency reserve to the cost estimate, you get the cost baseline.
Cost Baseline = Cost Estimate + Contingency Reserve
请注意,该项目的性能将根据成本基准来衡量。
项目预算
If you add the management reserve to the cost baseline, you will get the project budget.
项目预算= Cost Baseline + Management Reserve
When You Cannot Use the Management Reserve
Management reserve and contingency reserve are different and serve different purposes.
Below are a few cases where you should not use the management reserve.
When You Are Over Budget
You have to estimate the new budget and try to get it approved. You should never use the management reserve to compensate for cost overrun.
The management reserve is for unidentified risks, not to cover the cost overrun.
While Using Schedule Compression Techniques
There are two安排压缩技术: fast tracking and crashing.
Schedule compression may lead to new risks. Identify those risks, prepare a response plan, and calculate the new contingency reserve. You will need to get it approved.
You can revisit your management reserve for a review as well.
However, in crashing, you use extra resources. After you complete the planning for crashing, you have to revisit your risk management planning.
镀金
You should avoidgold platingand you should not use the management reserve for it, this increases the risk and changes the scope.
后备计划
I often receive emails from my visitors asking me why we cannot use the management reserve for the fallback plan.
By definition, the management reserve is used for unknown risks.
A后备计划is not used for unknown risks; it is a plan for known risks when the primary response plan fails. Therefore, you will use the contingency reserve for this plan, not the management reserve.
残留风险
Since residual risks are identified risks, you will use contingency reserve to manage these risks.
The Difference Between Contingency Reserve and Management Reserve
The following are a few differences between the contingency reserve and management reserve:
- The contingency reserve is used to manage identified risks, while the management reserve is used for unidentified risks.
- The contingency reserve is an estimated figure, while the management reserve is a percentage of the cost or duration of the project.
- The project manager has authority over the contingency reserve, while for the management reserve, they need management’s permission.
- The contingency reserve is a part of the performance measurement baseline, while the management reserve is not.
Summary
来complete your project successfully, you will have to be proactive in risk management. The contingency reserve and management reserve are the backbones of your risk management, as they provide you with the means to manage risks. The contingency reserve and management reserve are not the same; they are calculated with different techniques and serve different purposes. The contingency reserve is for identified risks and is a part of your cost baseline while the management reserve is for unidentified risks and is a part of your budget.
This topic is important from a PMP and PMI-RMP exam point of view. You may see a few questions on this topic in your exam.
How do you calculate the management reserve and contingency reserve on your projects? Please share your thoughts in the comments section.
I am Mohammad Fahad Usmani, B.E. PMP, PMI-RMP. I have been blogging on project management topics since 2011. To date, thousands of professionals have passed the PMP exam using my resources.
Hi Fahad
我不确定如果所有确定的EMV wi风险ll be part of the contingency reserve. The Contingency reserve is associated with the Active Acceptance of the risk. The Project Manager prepares a contingent plan with pre-set triggers and contingency budget is set to execute this plan. However, the cost to mitigate any threat should be part of the project cost and not of the contingency reserve. Will you please give reference to the PMBOK which states that EMV of all identified risk without a risk mitigation should be part of the contingent reserve?
You may not create a contingency reserve for risks who are in watch list or you decide to passively accept them.
法哈德 -
I am having trouble deciphering the following from PMP book. Any help would be appreciated.
1.在PG上。173,它指出活动成本估计可能包括应急准备金……然后说应急储备是资金要求的一部分。然后在PG上。177它提到项目成本基线中不包括储备金,而可以包含在总项目Budge中?撇开管理储备的问题,是否包含成本基线中的应急储备?我们如何在PMBOK 4中调和这两个不同的冲突段落?
2.应变储备是否分层?换句话说,我们是否在活动级别上有应急储备,然后在工作包 /控制帐户级别的应急储备?
3. (optional question if you can answer): If time spent on the project = cost incurred, then we have activity duration estimation reserves as well as activity cost reserves (both of these amount to additional cost from pure economic perspective)? Isn’t this double dipping or both of these reserves are reconciled at some point in the project?
4. Lastly, in the practical world, do project managers maintain 2 different cost buckets for each work package: original cost & contingency reserve or both of them are merged into one cost number for a package?
Thanks
1. On page-173, the PMBOK is talking about the contingency reserve that cost estimate may include the contingency reserve. On page-177, the PMBOK Guide is talking about the management reserve that it is not included in the cost baseline but in the total budget. Contingency reserve is included in the cost baseline while management reserve is not.
budget = cost baseline + management reserve
2. Contingency reserve is a pool of amount which is utilized when any identified risk occurs. Contingency reserve is calculated for whole project considering positive risk and negative risks.
3. The way you have calculated the contingency reserve for cost, you also have to calculate the contingency reserve for schedule, here they are called time reserve of buffers. Please see page-151 PMBOK 4th edition.
4. Answer for this point is melted in above explanation.
希望能帮助到你。
Hello Fahad,
I have a question on CR. CR, as we all know, are the reserves used to cover the costs of known-unknowns. It is said that CR is calculated using EVM, which is a part of Perform Quantitative Analysis process of Risk Management. Now, we also know that this process is optional – if the cost of doing Perform Quantitative Analysis is high, it can be skipped altogether. Does it mean that calculating CR without doing a quantitative analysis a guesswork?
sumeet
The process for establishing Contingency Reserve is established in the Risk Management Plan. It can be set using EMV, but that’s not required. Some organizations set the contingency as a fixed rate (e.g. 10%). Others set it using a risk model (generally a high-level questionnaire to determine the relative level of risk compared to other projects). And yes, some set it using expected value.
The key is to know which process you’re going to apply. If you are ONLY going to use EMV, then you need to set down Quantitative Analysis as a process step that shall not be skipped. If you’re going to use some other metric to set it, you’re free to include or exclude the Quantitative Analysis.
希望能帮助到你。
谢谢Fahad,这肯定会有所帮助!
Hi Fahad,
I’m new to this area of project management, so apologies if this seems like a silly question! Since the Contingency Reserve is calculated as a percentage of the impact of the risk occurring, the reserves are never actually going to cover the impact if the risk does actually occur, correct?
So if the risk does occur, the effort to resolve the risk means your contingency will be used AND you will also have a deviation from your cost baseline? While I appreciate that you can’t factor in the complete cost of every risk, I’m having difficulty in seeing the logic of this method of estimating contingency reserves when it seems like they will never completely cover the cost of ANY risk?
Is it possibly the assumption that, if the risk was to occur, that the contingency plan for a risk factors in additional activities to reduce the cost of the impact, meaning that when combined with the contingency plan, the contingency reserves do actually cover the cost of the risk?
Kind Regards,
Eoin
Hello Eoin,
首先,您应该了解,可以将风险作为大量事件(宏)的总体管理,也可以按事件(微观)进行管理。
In project management, Risk Management is managed by considering a large population of events.
Now, come to your point:
假设您已经确定了一百numbers of risks and then calculated the impact of these risks if they happen to occur. Then you multiply the impact by their respective likelihood and add them all to get the contingency reserve.
Now, do you really think that these all hundred identified risks are going to occur on your project? No, there is very less chance for this to happen.
点是,其中一些会发生,而休息将不会发生。如果发生任何风险,您可以从应急储备中拿走钱。
There will not be any deviation from the cost baseline unless you spend all of your contingency reserve.
Hi Fahad,
Thanks for the reply on this, what got me about the examples I saw on this section is that there was never enough contingency to cover if even a single risk occurred.
Take a simple scenario where you have identified 6 risks, all with a €10,000 impact and 10% chance of occurrence, if just one of these risks occurred, all your contingency is used up and you still have not covered the cost of the risk!
I take the point that in a larger project the number of risks is much larger, therefore your contingency reserve will be more likely to cover the cost of risks occurring, perhaps the examples involving smaller numbers of risks are just not realistic?
Hello Eoin,
As I said earlier that Project Risk Management is managed by considering a large population of events.
As the population grows, better the Risk Management Plan.
希望能帮助到你。
Fahad
If the allocated cost of a contingency plan for a single risk event exceeds the total remaining funds in a contingency reserve, where the contingency reserve is managed in aggregate (sum of probability x impact for all accepted risks with contingency plans), then I think there would be a strong case to treat this as an unknown-known. I generally consider these planning errors, but in this case, the planner is not necessarily at fault, since allocating funds for the contingency reserve must be balanced against the statistically expected cost for the risks in order to keep an acceptable cost baseline.
I would suggest that the minimum amount for the contingency reserve should always be enough to cover the largest remaining risk in the contingency plan. So in your example, instead of establishing a €6,000 contingency reserve (6 x €10,000 x 10%), impose a constraint that the contingency reserve is never less than €10,000 until that last trigger event is safely in the rearview mirror.
It is your project and you have to manage it. The PMBOK Guides equip you with the best industry knowledge so that you can complete the project successfully.
Develop the project plan as per your knowledge and understanding, get it approved and stick to it.
首先,感谢您的帖子。我的疑问是:
假设存在确定风险的应急计划,并且随后发生了风险,在这种情况下,我的时间表将考虑到偶然性。那么,我们是否必须执行集成的变更控制,将其带到顾问委员会,获得批准然后更改基线?- 因为有确定的风险
发生..
在这种情况下,我们是否使用管理储备金或应急储备?如果是应急储备,那么当我的基线仍在改变时,它的用途是什么?
Thanks in advance.
Hello Anmol,
If any identified risk occurs, you implement the approved contingency plan. In this case you will not go for schedule change because risk was already identified and it was already factored in your schedule.
For identified risks, Contingency Reserve is used. Management Reserve is for unidentified risks.
There is no change in the baseline unless you spend all contingency reserve.
不错的帖子,但是如果我有其发生的风险和概率,我该如何计算应急和管理储备?
你好诺拉,
来calculate Contingency Reserve, you must have probability of each risk and its impact. Once you get it, multiply probability to its impact. Repeat this procedure for all risks and then add it. Result will be your contingency reserve.
管理储备是该项目成本的一定比例。它可能在5%至10%之间变化。
I have one Question regarding Secondary Risk , is it covered by Contingency Or Management reserve ?
Thank you
Since it is a known or identified risk, it is covered under contingency reserve.
我有undersrtood以下:
1. Neither the CR or the MR are included in the cost baseline.
2. The CR is included in the project's budget (i.e., required funding)
3. The MR is not incliuded in the project's budget (i.e., required funding)The exposure draft of the 5th Edition of the PMBOK Guide espouses the following
1. The CR is included in the cost baselne
2. The MR is not included in the cost baseline, but is included in project's budget (i.e., required funding)
What are your thoughts?
As per the PMBOK Guide 4th Edition,
Cost base line is the sum of project cost estimate and contingency reserve; i.e.
Cost Baseline = Project Cost Estimate + Contingency Reserve
And, project budget is the sum of project cost base line and the management reserve; i.e.
项目预算= Cost Baseline + Management Reserve
Therefore, Management Reserve is not a part of the cost baseline but it is a part of the project budget and Contingency Reserve is a part of cost baseline as well as project budget.
Hope it answers your query.
Since, I’ve not reviewed the exposure draft of the PMBOK Guide 5th edition thoroughly, I would not comment on it. However, the information provided by you here in comment section is agreeing with the current version of the PMBOK Guide; i.e. 4th edition.
另一个后续问题:
If a negative risk (theat) is actively accepted, good practice would require that we develop a contingent plan of action (response) that woulf be executed should thwe risk be realized. The implementation of that response would require that we use established formal change control procedures to modify the scope, schedule and/or cost baselines as necessary. If a modification of the cost baseline is needed.and we have estiblished both a Contingency Reserve and a Management Reserve of money, where would the funds to cover the contingent response come from?
If any identified risk occurs then fund from the Contingency Reserves will be used, otherwise Management Reserved will be used but only after taking the required approval from the management.
It is a fact that the cost baseline is the sum of the cost estimates of each work package. Every dollar of the cost baseline must be linked to a component of the projects scope. If, as you replied earlier, the Contingency Reserve (CR) funds are included in the baseline, what element of scope are they tied to before possibly being moved to funding a contingent response for an actively accepted risk?.
The PMBOK Guide 4th Edition, Page 173, Article 7.1.2.6 says,
"Cost estimates may include contingency reserves (sometimes called contingency allowances) to
account for cost uncertainty."
This is a separate reserve, known as a CR and this reserve is not tied with anything. Just a calculated reserve for identified risks.
Scott Freauf says
June 25, 2012 at 9:08 PM
我有undersrtood以下:
1. Neither the CR or the MR are included in the cost baseline.
2. CR包括在项目的预算中(即所需资金)
3. The MR is not incliuded in the project’s budget (i.e., required funding)The exposure draft of the 5th Edition of the PMBOK Guide espouses the following
1. The CR is included in the cost baselne
2. The MR is not included in the cost baseline, but is included in project’s budget (i.e., required funding)
What are your thoughts?
Does 3 not contradict the second 2. The MR is not included in the cost baseline, but is included in project’s budget (i.e., required funding)
What are your thoughts?
请参阅第213页,PMBOK指南第五版和图表。bob手机客户端您将对CR,MR,成本基线和项目预算的所有疑问。