Today we will discussresidual risks vs secondary risks。
I have explained the residual risk and secondary risk in my post onthe type of risk。但是我已经看到许多专业人员在理解这两个方面都有问题。
Let’s look at both risk management concepts in detail
剩余风险与次要风险
许多专业人士认为,剩余风险和次要风险是未知的风险,如果出现后,我们会使用后备计划和管理储备。
Please understand this: residual and secondary risks are identified risks. You will carry out the contingency plan if any identified risk occurs, then apply the fallback plan if the contingency plan fails.
在这两种情况下,您都将使用应急储备,因为它是用于确定的风险。管理储备是针对身份不明的风险。
让我们深入研究。
残留风险
你已经确定了风险和开发了一个反应plan. However, when this does not completely remove the risk, the remainder is called residual risk.
According to the PMBOK Guide, “residual risks are those risks that are expected to remain after the planned responses of risks have been taken, as well as those that have been deliberately accepted.”
Example of a Residual Risk
Let’s say you have identified that it may rain for one to two hours. Therefore, you have created a contingency plan to manage this risk.
但是,如果雨水落下两个多小时,会发生什么?
You have to develop a fallback plan.
This is an example of residual risk.
As a project manager, you must evaluate residual risks properly. If it is a low priority, keep it on the watch list. You will develop a risk response plan to mitigate the impact of high-priority risk.
Please note that for all risks, if the trigger hits, you will implement the response plan. This plan can be a contingency or a fallback plan.
您将实施主要或次要风险的应急计划以及剩余风险的后备计划。
如果发生这些风险,您将使用应急储备,而不是管理储备。应急储备是针对已确定的风险,管理储备适用于身份不明的风险。
Secondary Risks
A risk is an uncertain event that can affect your项目目标。
You will develop a risk response plan to manage it. Often, this response can create a new risk, a secondary risk.
According to the PMBOK Guide, “Secondary risks are those risks that arise as a direct result of implementing a risk response.”
Simply put, your response plan for risk caused a new risk. The new risk is known as a secondary risk.
Example of Secondary Risks
Let’s say you have excavated a trench to stop animals. However, it’s possible that pedestrians may fall into the trench.
This is an example of secondary risk.
If your response plan creates a secondary risk, you will analyze it and develop arisk response plan, if required.
If the impact is very low, you will just keep it on the watch list.
概括
剩余和次要风险通常被忽略,项目经理不会制定响应计划。他们仅专注于主要风险。不要这样做。次要和残留风险同样重要。忽略它们会危害您的项目的成功。
Here is where the post on residual risk vs secondary risk ends, and I hope I’ve illuminated the differences for you.
Please share your experience with managing secondary and residual risks in the comments section.
Mr. Fahad
您在博客中提到,倒退计划用于剩余风险。但是,根据我理解的,仅在应急计划不足以解决问题的情况下才使用倒退计划。
Please correct me if i am wrong.
Please refer to the following blog post:
//www.utahfilmbank.com/2012/02/contingency-plan-vs-fallback-plan/
hi all,
I have some queries on the priorities regards to risk, hope someone can advise me
q1)当触发风险,我们第一次做
a) inform the stakeholder , or
b) implement the risk response plan
q2) when a new risk occur, do we (which is first, second and third)
a) update in the risk register
b) analyse the impact
c) inform the stakeholder
When the trigger occurs, risk action owner will take the action and implement the risk response plan.
When any new (un-identified) risk occurs, you will manage it through workaround.
Thanks Fahad!
for un-identified risk, I had thought we have to analyze the impact first before anything?
for both of my questions, I assume ‘notifying stakeholder’ is NOT the first thing to do.
You are welcome Martin.
Hi Fahad,
感谢您精确地解释博客中的残留和次要风险。我的问题是关于次要风险。次要风险的风险响应计划的名称是什么?例如,我们制定了主要风险的应急计划。我试图了解是否有任何类似的响应计划可用于次要风险?
问候,
Bala
Since these are identified risks, they will be covered in contingency plan.
Risks that are caused by the response to another risk is Residual or Secondary Risks.
Iam trying to buy 400pmp exam sample qs . but is not possible. pl let me how we can get it
From the below given link you can buy the PMP Question Bank.
//www.utahfilmbank.com/pmp-question-bank/
Hi
Residual risk : what is ‘leftover’ after implementing a contingency plan
Secondary risk: New risk after implementing a contingency plan
So, if you sub contract out a piece of work to another contractor (transfer), if the contractor go bust, is that a residual risk or secondary risk. For me, it sounds like a secondary risk.
but if the contractor were to have some delay to its deliverable to your project, it is seen as a residual risk.
评论s?
The first case represents a “residual” risk, because the risk impact stays the same (choosing transfer as risk response is mainly to minimize the liability or to address a technical/ expertise gap in the company), so this will stay the same for the 1st case, thus it is a residual risk. As for the 2nd case, it is a secondary risk since the risk impact is different than primary risk impact. In this case, the impact could be delays to project schedule.
I hope this makes sense
Fahad – Your study notes which are basically an expert clarification has helped alot to me, i could review it time to time to check my understanding and i cleared my PMP exam with (2 Moderately Proficient and 3 Proficient) in my first attempt.
You are giving a great service to this community. God bless you.
Congratulation Nitesh for passing the PMP exam. I’m glad that my blog helped you in your study.
太感谢了!这会很好地打破!!
You’re welcome Niikay…
请解释B/W退后计划的差异,解决方案和应急计划……都是一样的吗?
Regarding fall back and contingency plan, you can read this blog post:
//www.utahfilmbank.com/2012/02/contingency-plan-vs-fallback-plan/
And, workaround is an adhoc response when any unidentified risk occurs.
Thank you very much Fahad for your explanation . But I confused when can use response plan and contingency plan ??!!
这两个计划(contingency and fall back) are risk response plan.
Fahad,
感谢您的博客,我还购买了您的书《 PMP问题库》,到目前为止,我的平均值约为82%(我的目标是85%)。如果我错了,请纠正我,最初我认为应急储备被接受 - 至少这就是我认为当使用主动风险时,我认为我在另一本书中读过的内容)。然后我意识到事实并非如此,而是在使用“降低风险”时基本上适用的,而残留或次要风险仍然存在或存在。
Is my thought process wrong; kindly assist.
Btw, do you have other books of questions for the PMP exam, if, I would like to know how to obtain them.
VR
Yes. Contingency reserve is used for identified risks. Primary risks, secondary risks, residual risks, these are all identified risks.
不,我没有其他问题库接受您已经拥有的问题。
Good luck on your PMP exam.