Residual Risks vs Secondary Risks

residual-risk-vs-secondary-risk

Today we will discuss residual risks vs secondary risks.

I have explained the residual risk and secondary risk in my post onthe type of risk. But I have seen many professionals have issues with understanding these two.

Let’s look at both risk management concepts in detail

Residual Risks vs Secondary Risks

Many professionals think residual and secondary risks are unknown risks and that we use a fallback plan and management reserve if they occur.

Please understand this: residual and secondary risks are identified risks. You will carry out the contingency plan if any identified risk occurs, then apply the fallback plan if the contingency plan fails.

In both cases, you will use the contingency reserve because it is for identified risks. Management reserves are for unidentified risks.

Let’s dive deeper.

Residual Risks

You have identified risks and developed a response plan. However, when this does not completely remove the risk, the remainder is called residual risk.

According to the PMBOK Guide, “residual risks are those risks that are expected to remain after the planned responses of risks have been taken, as well as those that have been deliberately accepted.”

Example of a Residual Risk

Let’s say you have identified that it may rain for one to two hours. Therefore, you have created a contingency plan to manage this risk.

But, what happens if the rain falls for over two hours?

You have to develop a fallback plan.

This is an example of residual risk.

As a project manager, you must ensure that residual risks are evaluated properly. If it is a low priority, keep it on the watch list. You will develop a risk response plan to mitigate the impact of high-priority risk.

Please note that for all risks, if the trigger hits, you will implement the response plan. This plan can be a contingency or a fallback plan.

You will implement the contingency plan for a primary or secondary risk, and the fallback plan for residual risk.

You will use the contingency reserve if any of these risks occur, not the management reserve.The contingency reserve is for identified risks, and the management reserve is for unidentified risks.

Secondary Risks

A risk is an uncertain event that can affect your project objectives.

You will develop a risk response plan to manage it. Often, this response can create a new risk, a secondary risk.

According to the PMBOK Guide, “Secondary risks are those risks that arise as a direct result of implementing a risk response.”

Simply put, your response plan for risk caused a new risk. The new risk is known as a secondary risk.

Example of Secondary Risks

Let’s say you have excavated a trench to stop animals. However, it’s possible that pedestrians may fall into the trench.

This is an example of secondary risk.

If your response plan creates a secondary risk, you will analyze it and develop arisk response plan, if required.

If the impact is very low, you will just keep it on the watch list.

Summary

Residual and secondary risks are often ignored, and project managers don’t develop a response plan. They only focus only on primary risks. Don’t do this. Secondary and residual risks are equally important. Ignoring them will jeopardize your project’s success.

Here is where the post on residual risk vs secondary risk ends, and I hope I’ve illuminated the differences for you.

Please share your experience with managing secondary and residual risks in the comments section.


  • Mr. Fahad

    You mentioned in your blog that fall back plan are used for residual risks . But as per what i understand fall back plan are used only if the contingency plan is inadequate to solve the problem.

    Please correct me if i am wrong.

  • hi all,

    我有一些,ries on the priorities regards to risk, hope someone can advise me

    q1) when a risk triggered, do we first
    a) inform the stakeholder , or
    b) implement the risk response plan

    q2) when a new risk occur, do we (which is first, second and third)
    a) update in the risk register
    b) analyse the impact
    c) inform the stakeholder

    • When the trigger occurs, risk action owner will take the action and implement the risk response plan.

      When any new (un-identified) risk occurs, you will manage it through workaround.

  • 嗨法赫德,
    Thank you for precisely explaining residual and secondary risk in your blog. My question is regarding secondary risk. what is the name of the risk response plan for the secondary risk? For example, we have a contingency plan for primary risk. I am trying to understand is there any such similar response plan available for secondary risk?
    Regards,
    Bala

  • Risks that are caused by the response to another risk is Residual or Secondary Risks.

    Iam trying to buy 400pmp exam sample qs . but is not possible. pl let me how we can get it

  • Hi

    Residual risk : what is ‘leftover’ after implementing a contingency plan
    Secondary risk: New risk after implementing a contingency plan

    So, if you sub contract out a piece of work to another contractor (transfer), if the contractor go bust, is that a residual risk or secondary risk. For me, it sounds like a secondary risk.

    but if the contractor were to have some delay to its deliverable to your project, it is seen as a residual risk.

    Comments?

    • The first case represents a “residual” risk, because the risk impact stays the same (choosing transfer as risk response is mainly to minimize the liability or to address a technical/ expertise gap in the company), so this will stay the same for the 1st case, thus it is a residual risk. As for the 2nd case, it is a secondary risk since the risk impact is different than primary risk impact. In this case, the impact could be delays to project schedule.
      I hope this makes sense

  • Fahad – Your study notes which are basically an expert clarification has helped alot to me, i could review it time to time to check my understanding and i cleared my PMP exam with (2 Moderately Proficient and 3 Proficient) in my first attempt.
    You are giving a great service to this community. God bless you.

  • Please explain the difference b/w fall back plan, work around and contingency plan …all are same ?

  • Thank you very much Fahad for your explanation . But I confused when can use response plan and contingency plan ??!!

      • Fahad,
        Thanks for your blog, I also bought your book the PMP Question Bank and so far, I am averaging approximately 82% (my goal is 85%). Kindly correct me if I am wrong, initially I thought contingency reserves were used for accepted– at least that’s what I think I read in another book-used when a proactive risk approached is being used). Then I realized this is not the case, but it rather applies when basically when using ” risk mitigation” where residual or secondary risks remain or come to existence.

        Is my thought process wrong; kindly assist.

        Btw, do you have other books of questions for the PMP exam, if, I would like to know how to obtain them.

        VR

        • Yes. Contingency reserve is used for identified risks. Primary risks, secondary risks, residual risks, these are all identified risks.

          No, I don’t have any other question bank accept the one that you already have with you.

          Good luck on your PMP exam.

  • {“电子邮件”:“邮件地址无效”,“url”:”网站的广告dress invalid","required":"Required field missing"}

    Recommended Resources

    Use these resources for your PMP certification exam preparation and pass the exam with minimal effort.

    The PMP Training Program


    The PMI approved 35 contact hours training program that is 100% online, affordable, and help you prepare the PMP exam.

    The PMP Exam Preparation Tool


    A PMP exam preparation course, that is 100% online and provide you everything you need to pass the PMP exam.

    >