residual-risk-vs-secondary-risk

今天我们将讨论残余风险vs次生风险

我已经解释了我的帖子中的残留风险和次要风险风险类型。But I have seen many professionals have issues with understanding these two.

让我们详细了解两个风险管理概念

再保险sidual Risks Vs Secondary Risks

Many professionals think residual and secondary risks are unknown risks and that we use a fallback plan and management reserve if they occur.

请理解这一点:确定剩余风险和次要风险。如果发生任何已确定的风险,您将执行应急计划,然后如果应急计划失败,请应用后备计划。

In both cases, you will use the contingency reserve because it is for identified risks. Management reserves are for unidentified risks.

Let’s dive deeper.

再保险sidual Risks

您已经确定了风险并制定了响应计划。但是,当这并不能完全消除风险时,其余称为剩余风险。

根据PMBOK指南,“剩余风险是在bob手机客户端计划采取风险以及被故意接受的风险响应后仍会保留的那些风险。”

Example of a Residual Risk

Let’s say you have identified that it may rain for one to two hours. Therefore, you have created a contingency plan to manage this risk.

But, what happens if the rain falls for over two hours?

You have to develop a fallback plan.

这是残余风险的一个例子。

作为项目经理,您必须正确评估剩余风险。如果优先级较低,请将其保留在观察列表中。您将制定风险响应计划,以减轻高优先级风险的影响。

Please note that for all risks, if the trigger hits, you will implement the response plan. This plan can be a contingency or a fallback plan.

You will implement the contingency plan for a primary or secondary risk and the fallback plan for residual risk.

You will use the contingency reserve if these risks occur, not the management reserve.The contingency reserve is for identified risks, and the management reserve is for unidentified risks

Secondary Risks

风险是一个不确定的事件,会影响您的project objectives

You will develop a risk response plan to manage it. Often, this response can create a new risk, a secondary risk.

根据《 PMBOK指南》,“次要风bob手机客户端险是发生风险响应的直接结果的风险。”

简而言之,您对风险的响应计划引起了新的风险。新风险被称为第二风险。

Example of Secondary Risks

Let’s say you have excavated a trench to stop animals. However, it’s possible that pedestrians may fall into the trench.

这是次要风险的一个例子。

如果您的响应计划造成了次要风险,您将分析并开发一个风险响应计划, 如果需要的话。

如果影响很低,您只需将其保留在观察列表中即可。

Summary

再保险sidual and secondary risks are often ignored, and project managers don’t develop a response plan. They only focus only on primary risks. Don’t do this. Secondary and residual risks are equally important. Ignoring them will jeopardize your project’s success.

这是关于残留风险与次要风险结束的帖子的地方,我希望我为您照亮了差异。

Please share your experience with managing secondary and residual risks in the comments section.