通常认为风险与该区域的不确定性相同风险管理。一种lthough there is a big difference between risk and uncertainty, many professionals often think they are the same.
尽管从PMP或PMI-RMP考试的角度来看,这个概念并不重要,但您必须理解差异以避免混合它们。
Therefore, I’m writing this blog post to explain it and I hope after reading it, you won’t have any problems distinguishing between risk and uncertainty.
风险
一种风险is an unplanned event that may affect one or some ofyour projectobjectives if it occurs. The risk is positive if it affects your project positively, and it is negative if it affects the project negatively.
负面的否定性和积极因素有单独的风险反应策略。
The objective of a负风险反应策略是为了最大程度地减少其影响或概率,而正风险反应策略是最大化机会或影响。
You might also hear two more risk terms: known and unknown. Known risks are identified during the identify risks process and unknown risks are those you couldn’t identify.
一种应急方案is made for known risks, and you will use the contingency reserve to manage them. On the other hand, unknown risks are managed through a解决方法using themanagement reserve。
Uncertainty
不确定性是缺乏完全确定性。在不确定的情况下,任何事件的结果都是完全未知的,并且不能衡量或猜测。您没有有关活动的任何背景信息。
不确定性不是未知的风险。
In uncertainty, you completely lack the background information of an event, even though it has been identified. In the case of unknown risk, although you have the background information, you missed it during the identify risks process.
一种Real-World Example of Risk and Uncertainty
一种ssume two famous teams consist of renowned players, and they are going to play a football match the next day.
您能告诉我哪支球队将要赢得胜利?
不,你不能;但是,您可以通过审查和分析每个球员,团队以及他们相互对抗的比赛结果的过去表现来进行良好的猜测。
然后,您可以提出一些数字,例如A或B队赢得30%的机会,或者有70%的A或B团队输掉比赛的可能性。
现在,让我们在不同的情况下进行相同的足球比赛。
Let us say again that two teams are going to play a game, and no players are selected for either team.
在这种情况下,如果有人问您要赢得哪支球队,您的回应将是什么?
You will be clueless because you don’t know which team consists of which players, and you have no idea how the teams will perform.
在这里,即使规则和体育场是相同的,您也没有任何有关过去绩效的信息,也无法预测事件的结果。
这种情况称为不确定性。
风险Vs Uncertainty
以下是风险和不确定性之间的一些差异:
- 在风险下,您可以预测未来结果的可能性,而在不确定性下,您不能。
- 在不确定性无法控制的情况下,可以管理风险。
- 可以测量和量化风险,而不确定性则不能。
- 您可以为风险事件分配概率,而不确定性则不能。
Conclusion
风险和不确定性是不同的术语,但人们倾向于混淆它们。管理风险更容易,因为您可以根据自己的经验来识别它们并制定响应计划。但是,管理不确定性非常困难,因为以前的信息没有可用,涉及太多参数,并且您无法预测结果。
但是,要成功完成您的项目,您必须非常谨慎,积极主动且开放,以管理风险和不确定性。
这是风险与不确定性职位结束的地方。希望现在您可以将不确定性与风险区分开。仍然有一些疑问,在评论部分中发布它们,我会回复您。
by identifies risk and I must proactive to the uncertainty event by doing this my project will be successfully doing.
您应该主动在风险管理方面。它肯定会帮助您成功完成项目。
数学上
风险=不确定的事件,如果发生会影响事件的结果,以正方向或负面方向影响事件
所以有两个部分
风险=概率 *影响
现在,在概率理论下,事件可以以三种方式发生
1)它将发生(某个事件)prob = 1,撞击您可以根据发现以找到风险输入
2) It may occur ( a probable event, however small it could be, those who talk about unknown unknowns or uncertainties all fall here) the probability could be infinitesimal or we just ignore it as It’s not worth * impact = get the risk value .
3)不会发生(不可能发生的事件,零概率) *影响=无关的风险。
外面没有什么。这些不确定性甚至我们可能不会想到或想象也将属于它,但只担心可能影响我们项目的主要可能事件。
您的生活中有数百万个变量都不确定,甚至震动我们的变量可能有可能,但我们并没有真正考虑每天的风险,但是那些不那么幸运且震惊的人,尽管无限的概率是他们松动的。
每个事件是否已知和未知事件都有发生的概率,并且总计1。
现在您选择样品空间是什么?
维诺德说。
抱歉,我不同意您使用的基本定义。首先,不确定性是定义任何已知或未知事件或一系列事件的伞术语。它包括津贴,应急和风险。津贴是“已知的”,其确切值在当时尚不清楚,但其支出肯定会发生。因此,将金额分配给此特定费用,然后在可用的其他信息时重新审视。偶然性是定义项目范围内的“知名度不佳”。这是针对定义项目范围内不可预见的成本要素的特定规定,尤其重要的是,在先前的经验与估计和实际成本相关的经验表明,增加成本的不可预见的事件可能会发生(AACEI)(AACEI)。应急事件估计是根据该估计的主题专家(SME)的经验判断进行的。风险是“未知的未知”,其发生的可能性和成本影响不确定。但是,即使是未知的知名度也可以通过中小企业估计,根据他们使用蒙特卡洛计算机模型的经验来估计发生的可能性和影响的估计值。 The Risk Register is where the risks (or opportunities) are listed and discussed in a Risk Workshop of SMEs, and both qualitative and quantitative descriptions are assigned to each risk element. The risk elements are prioritized, and the SMEs then look for mitigation measures to reduce or eliminate each risk. The residual post-mitigation risks are then used as the basis for the Monte Carlo computer analysis. The analysis will return the calculation that there is a (say) 80% probability that the total cost of the risks will be less than $ X thousand, or other percentages and impact cost depending on the risk estimator’s (or management’s) risk appetite. This amount should be added to the Project Base Cost (which would include Allowances) and the Contingency, defined as the Project Baseline Cost, to arrive at the project funded (or budgeted) cost.
For a more complete treatise on Uncertainty which I co-authored, please read “Addressing Uncertainties in Cost Estimates for Decommissioning Nuclear Facilities,” © OECD 2017, NEA No. 7344.
这些定义基于PMBOK指南第五版。bob手机客户端
除非你们已经决定,除非您已经决定项目管理的不确定性定义与其他人类努力(如科学,工程和医学)的定义不同,否则我建议阅读有关该主题的众多书籍中的一些。当然可以测量不确定性,并在严重的领域中使用,以分配结果将在定义范围内发生的概率。
Google uncertainty in science or uncertainty budget
I fear you may have got some of your info from the field of economics (which can make astrology and black magic look bad) ;)
Can you explain it little further:
当然可以测量不确定性,并在严重的领域中使用,以分配结果将在定义范围内发生的概率。
感谢您分享有关风险和不确定性的想法。天使所说的与您正确和简单的想法没有什么不同。差异仅在声明中,但你们俩都表现出了相同的差异。感谢您使我更加清楚这个主题。
在不确定你完全缺乏的历史and pas information. The construction of a house or painting a wall does not fall in this category. Here you can estimate the cost will a good accuracy. Most of the times these contracts are given under fixed price or cost reimbursable.
在风险下,您可以猜测结果,但在不确定性方面做不到。
有人可以告诉我风险和不确定性的关系吗
可以说风险是一个不确定的事件,可以预测和衡量发生发生的机会,而不确定性也可以说是不确定的事件,无法预测和衡量发生的机会。区别在于,可以预测和测量发生风险事件的概率,而不确定性的概率无法预测和测量。
法哈德
我们可以说,应对负面风险的应急计划,而管理储备专用于不确定的问题,因为我们无法猜测它们的影响?
这是一个棘手的问题。
根据我的理解,由于不确定性是确定的风险,因此您可以被动地接受不确定性,并根据受过教育的猜测保留一些应急储备。
我还要求其他访客分享他们对此的想法。
风险:我们不知道接下来会发生什么,但是我们确实知道分销的外观。
不确定性:我们不知道接下来会发生什么,我们不知道可能的分布是什么样的。
Correct….
在我看来,不确定性是不完美的知识。在整个项目中,我们努力提高定义(减少不确定性),以提高成功机会(减少失败的风险)。项目中有关键的不确定性,您必须在做出战略决策之前就必须很好地理解。
成本估算是一个很好的例子,可以说明不确定性。很难(如果不是不可能)估计复杂项目的最终成本到最后一分钱。您还记得您在家里做了一份改建工作的最后发生了什么事吗?如果您不太了解不确定性,您可能最终会后悔自己重塑厨房的决定。这就是为什么您进行前端工作:制定范围,准备计划,获得报价等。这是为了减少不确定性。
不确定性分析有助于我们了解结果的预期范围和针对项目目标的测试,以做出明智的决定。例如,我们可以测试一个项目是否对各种成本增长方案有弹性,并做出明智的决定来制裁该项目。然后,我们可以表征风险或机会。
很抱歉增加混乱,但我从根本上同意Angel。。
假设我们必须在厨房里画一堵墙。
最初(在计划阶段)我们不确定要使用的油漆量,但可以估计它是一个随机数
我们不确定绘画墙所花费的时间。
有风险,石膏会在准备中崩溃。
There is a risk that the paint will bubble after it has been applied.
不确定性是通过研究来管理的,并将Slack投入项目
负风险是通过流程改进和恢复策略来管理的。
事实,您可能会对发生风险事件的可能性不确定性:)
嗨,法哈德,
您能否帮助提供详细信息/执行定性和定量风险分析的差异?
谢谢,
纳文
在定性风险分析中,您可以通过增加风险的概率和影响来确定风险。在定量风险分析中,您可以数值分析风险。在这里,您会发现每种风险的成本(如果单独发生),然后将其添加以获得对项目的总体影响。
Thanks a lot !!!
在当今项目管理的情况下,风险和不确定性都是不可避免的。一个人必须在中途开车。
Yes, one has to chose the best path suitable to the project.